- Sections
- 31(7), 31, 34
Not a certified copy. Text extracted from the judgment PDF published by the Supreme Court of India. Verify against the certified copy before relying on it. Source: Supreme Court of India, via the Indian Supreme Court Judgments dataset by Dattam Labs (CC-BY-4.0). Retrieved 17 Nov 2026, 12:18 am. Original source ↗
Preview: first 50% of the document.
[2025] 9 S.C.R. 1378 : 2025 INSC 1148 HLV Limited (Formerly Known as Hotel Leelaventure Pvt. Ltd.)
v.
PBSAMP Projects Pvt. Ltd.
(Civil Appeal No. 12234 of 2025)
24 September 2025 [Manoj Misra and Ujjal Bhuyan,* JJ.] Issue for Consideration Whether in the facts and circumstances of the case, the decree holder (respondent) would be entitled to interest upon interest in terms of s.31(7)(b), Arbitration and Conciliation Act, 1996 or the interest awarded by the arbitral tribunal in the award in terms of the memorandum of understanding (MoU) entered into between the parties i.e. between the appellant and the respondent fulfil the requirement of s.31(7)(a) and (b) of the said Act.
Headnotes† Arbitration and Conciliation Act, 1996 – s.31(7)(a), (b) – High Court set aside the order of the Executing Court rejecting the petition filed by the respondent-decree holder for enforcement of the arbitral award on the ground that respondent is not entitled to compound interest and that the amount paid by the appellant-judgment debtor to the respondent was in full satisfaction of the award – Respondent, if entitled to interest upon interest in terms of s.31(7)(b) or the interest awarded by the arbitral tribunal in the award in terms of the MoU entered into between the parties fulfil the requirement of s.31(7)(a) and (b):
Held: 1.1 Clause 6(b) of the MoU expressly provided that in the event of termination of the MoU, the appellant must refund all advances with interest at the rate of 21% per annum from the respective dates of disbursement till repayment – Thus, in the light of the express provision contained in clause (a) of sub-section (7) of s.31, the arbitral tribunal awarded interest in terms of the MoU from the date of the cause of action till the date of repayment – As the arbitral tribunal had expressly provided interest till the date * Author [2025] 9 S.C.R. 1379HLV Limited (Formerly Known as Hotel Leelaventure Pvt. Ltd.) v. PBSAMP Projects Pvt. Ltd.
of repayment, question of additional or compound interest under clause (b) of sub-section (7) of s.31 would not arise. [Para 29] 1.2 Arbitral tribunal in its award complied with the MoU agreed by and between the parties – Thus, it exercised its discretion within the overall framework of s.31(7) aligning with the legislative intent that the award, rather than the statutory default, should govern the parties, more so in a case as in the present one where the parties themselves made provision for interest throughout. [Para 29] 1.3 Reliance placed by the respondent on Hyder Consulting case to claim post-award interest is misplaced – That principle would apply only when the arbitral tribunal leaves a matter unqualified or is silent – In the present case, the arbitral tribunal bound by the MoU and exercising its statutory discretion had already specified the interest rate (21% per annum) and the duration (until repayment). [Para 30] 1.4 The MoU did not stipulate compounding of interest; the arbitral tribunal did not award compound interest; therefore, respondent cannot at the stage of execution seek to introduce claim of compound interest by drawing on general principles. [Para 31] 1.5 High Court not justified in setting aside the order of the executing court and remanding the matter for fresh determination – Impugned judgment set aside – Order of the executing court restored. [Paras 32, 33] Arbitration and Conciliation Act, 1996 – s.31(7)(a), (b) – ‘sum’; ‘unless the award otherwise directs’:
Held: 1.1 From a conjoint analysis of s.31(7)(a) and s.31(7)(b), it is discernible that insofar award of interest from the date on which the cause of action arose till the date of the award is concerned, the legislative intent is that the parties possess the autonomy to determine the interest and the rate of interest for the aforesaid period – Clause (a) i.e. discretion of the arbitral tribunal to award interest is subject to agreement by and between the parties – Therefore, party autonomy takes precedence over the discretion of the arbitral tribunal. [Para 20] 1.2 However, clause (b) is subject to award of interest by the arbitral tribunal – As per clause (b), the ‘sum’ directed to be paid under an arbitral award shall carry interest at the rate of 18% per annum from the date of the award to the date of payment ‘unless the award otherwise directs’ – Therefore, this provision is subject 1380 [2025] 9 S.C.R.Supreme Court Reports to award of interest by the arbitral tribunal – If it awards interest, then the same shall be applicable from the date of the award till the date of payment; if not, then the ‘sum’ as adjudged under clause
(a) shall carry interest at the rate of 18%. [Para 20] Case Law Cited Hyder Consulting (UK) Limited v. Governor, State of Orissa [2014] 14 SCR 1029 : (2015) 2 SCC 189 – held inapplicable.
Morgan Securities and Credits Private Limited v. Videocon Industries Limited [2022] 9 SCR 819 : (2023) 1 SCC 602; Delhi Airport Metro Express Private Limited v. Delhi Metro Rail Corporation [2022] 3 SCR 716 : (2022) 9 SCC 286 – relied on.
North Delhi Municipal Corporation v. S.A. Builders Limited [2024] 12 SCR 1581 : (2025) 7 SCC 132; State of Haryana v. S.L. Arora, [2010] 2 SCR 297 : (2010) 3 SCC 690 – referred to.
List of Acts Arbitration and Conciliation Act, 1996.
List of Keywords Section 31(7)(a), (b), Arbitration and Conciliation Act, 1996; Interest upon interest; Compound interest; Stage of execution; Memorandum of understanding (MoU); Interest in terms of MoU; Termination of MoU; Arbitral tribunal bound by MoU; Interest till the date of repayment; Additional or compound interest; Post-award interest; Party autonomy; Executing Court.
Case Arising From CIVIL ORIGINAL JURISDICTION: Civil Appeal No. 12234 of 2025 From the Judgment and Order dated 22.04.2024 of the High Court for The State of Telangana at Hyderabad in CRP No. 60 of 2024 Appearances for Parties Advs. for the Appellant:
Dama Seshadri Naidu, Hemandranath Reddy, Sr. Advs., M Srinivas R Rao, M.V. Mukunda, Abid Ali Beeran P, Sarath S Janardanan, Saswat Adhyapak, Ms. Namita Kumari.
[2025] 9 S.C.R. 1381HLV Limited (Formerly Known as Hotel Leelaventure Pvt. Ltd.) v. PBSAMP Projects Pvt. Ltd.
Advs. for the Respondent:
P.b. Suresh, Sr. Adv., Mayank Jain, Madhur Jain, Ms. Aakriti Dhawan, Arpit Goel, Deepak Jain, Parmatma Singh.
Judgment / Order of the Supreme Court Judgment Ujjal Bhuyan, J.
Leave granted.
2. This appeal by special leave is directed against the judgment and order dated 22.04.2024 passed by the High Court for the State of Telangana at Hyderabad (High Court) in Civil Revision Petition No. 60 of 2024 (PBSAMP Projects Private Limited Vs. HLV Limited). By the impugned judgment and order, the Division Bench of the High Court set aside the order dated 02.11.2023 passed by the Principal Special Court in the cadre of District Judge for trial and disposal of commercial disputes at Hyderabad (referred to hereinafter as ‘the Executing Court’) in CEP No. 05 of 2021 rejecting the petition filed by the respondent for enforcement of the arbitral award dated 08.09.2019 on the ground that respondent is not entitled to compound interest and that the amount paid by the judgment debtor (appellant) to the decree holder (respondent) i.e. Rs. 44,42,05,254.00 was in full satisfaction of the award.
3. Question for consideration in this appeal is whether in the facts and circumstances of the case, the decree holder (respondent) would be entitled to interest upon interest in terms of Section 31(7)(b) of the Arbitration and Conciliation Act, 1996 or the interest awarded by the arbitral tribunal in the award dated 08.09.2019 in terms of the memorandum of understanding dated 09.04.2014 entered into between the parties i.e. between the appellant and the respondent fulfil the requirement of Section 31(7)(a) and (b) of the said Act?
4. The above question arises in the following factual backdrop.
5. The two parties had entered into a memorandum of understanding (MoU) on 09.04.2014. The MoU was with regard to sale and transfer of land situated at Road No. 10, Banjara Hills, Hyderabad admeasuring approximately 3 acres and 28 guntas. The details of the land are mentioned in the schedule to the MoU.
1382 [2025] 9 S.C.R.Supreme Court Reports
5.1. It may be mentioned that appellant as the vendor had acquired absolute ownership of the schedule land under different sale deeds which was to be used for construction of a five star hotel but for various reasons did not go ahead with the project and instead decided to sell the land to the respondent. Under the aforesaid MoU, respondent paid a sum of Rs. 15.5 crores as advance to the appellant. As differences arose between the parties, the MoU was terminated on 09.10.2024 whereafter the dispute was referred to arbitration. The arbitral tribunal comprised of three arbitrators: Mr. Justice TNC Rangarajan being nominated by the claimant i.e. the respondent and Mr. Justice A Kulasekaran being nominated by the appellant. The two arbitrators in turn nominated Justice Arijit Pasayat as the presiding arbitrator.
6. The arbitral tribunal passed an award dated 08th September, 2019, the operative portion of which reads as under:
The claimant is entitled to Rs. 15.5 crores with interest at 21% p.a. from the date it was given to the date it is repaid. The respondent has kept the documents of title in escrow for security purposes The respondent has admitted liability for Rs. 10 crores and disputed only the sum of Rs. 5.5 crores. Hence we direct that the respondent pay immediately the sum of Rs. 10 crores with interest The escrow arrangement will be limited to the disputed amount of Rs. 5.5 crores only. The claimant shall give the consent letter for release of the balance of Rs. 5.5 crores simultaneously with the tender of the amount by way of DD or certified cheque, NEFT/RTGS to a designated account by the respondent within 3 months from the date of the award. The amount will carry interest at 21% p.a. from the date it was received till the date of exchange of the DD, certified cheque, NEFT/RTGS with the consent letter. The respondent’s counterclaim stands rejected. In the peculiar facts of the case, it is directed that the parties shall bear their respective costs.
7. Thus, the arbitral tribunal awarded Rs. 15.5 crores to the claimant (respondent) with interest at the rate of 21 percent per annum from the date it was given to the date it is repaid. Appellant filed a petition [2025] 9 S.C.R. 1383HLV Limited (Formerly Known as Hotel Leelaventure Pvt. Ltd.) v. PBSAMP Projects Pvt. Ltd.
under Section 34 of the Arbitration and Conciliation Act, 1996 (briefly, ‘the 1996 Act’ hereinafter) before the learned Special Court for trial and disposal of commercial disputes at Hyderabad (Special Court) for setting aside of the award which was registered as COP No. 118 of 2019. Learned Special Court vide the judgment and order dated 19.03.2021 dismissed COP No. 118 of 2019.
8. It appears that there was no further challenge to the award. Thus, the arbitral award dated 08.09.2019 attained finality.
9. Thereafter, respondent filed execution petition CEP No. 05 of 2021 before the executing court for execution of the arbitral award dated 08.09.2019.
10. In the course of hearing, the judgment debtor (appellant) paid a total of Rs. 44,42,05,254.00 on various dates and in various amounts starting from 22.07.2022 to 31.07.2023 which according to it was in full compliance to the award including interest.
11. Decree holder i.e. the respondent filed a calculation sheet before the executing court claiming compound interest over and above the rate of interest i.e. 21 percent as awarded by the arbitral tribunal. The executing court referred to Section 31(7) of the 1996 Act as well as to the decision of this Court in Hyder Consulting (UK) Limited Vs. Governor, State of Orissa1 , and thereafter held that claim of the decree holder for compound interest on the awarded amount was not sustainable. The executing court cannot go beyond the award passed by the arbitral tribunal. The decree holder is not entitled for compound interest as claimed. The amount paid by the judgment debtor to the decree holder i.e. Rs. 44,42,05,254.00 was in full satisfaction of the arbitral award. Accordingly, by the order dated 02.11.2023 executing court closed CEP No. 05 of 2021.
12. This order came to be assailed by the respondent before the High Court in a proceeding under Article 227 of the Constitution of India which was registered as Civil Revision Petition No. 60 of 2024. By the impugned judgment and order dated 22.04.2024, the High Court was of the view that the executing court had reached the conclusion in a cryptic and cavalier manner. Therefore, the order dated 02.11.2023 was set aside and the matter was remitted back
1 (2015) 2 SCC 189
1384 [2025] 9 S.C.R.Supreme Court Reports to the executing court to reconsider the issue of interest under the award dated 08.09.2019 to the respondent though clarifying that it had not expressed any opinion on the merit of the claim.
13. Aggrieved, the related special leave petition came to be filed. This Court by order dated 14.05.2024 had issued notice and in the meanwhile, had stayed the order of remand.
14. Mr. Hemendranath Reddy, learned senior counsel for the appellant, at the outset, submits that the award neither granted compound interest nor granted post-award interest. Arbitral tribunal had awarded composite interest i.e. simple interest of 21% per annum from the dates payment became due to the date of repayment. Respondent did not challenge this part of the award. The award has since attained finality. Therefore, it is not open to the respondent now to claim either compound interest or post-award interest on the principal amount.
14.1. Mr. Reddy, learned senior counsel, submits that the executing court had specifically reasoned that the award had only granted 21% simple interest from the date when the cause of action arose till payment. For this entire period, the arbitral tribunal awarded simple interest at the rate of 21%. Neither any compound interest was granted nor any post-award interest. Therefore, respondent is not entitled to compound interest. This aspect of the matter was overlooked by the High Court which also did not consider the fact that the calculation submitted by the appellant was accepted by the executing court after due consideration of all the facts and circumstances of the case.
14.2. According to him, the reasoning given by the executing court cannot be faulted. Calculation offered by the appellant having been accepted by the executing court with sufficient reasons, the High Court was not justified in setting aside the order passed by the executing court and remanding the matter back for fresh consideration.
14.3. Learned senior counsel submits that by 31.07.2023, the entire amount of Rs. 44,42,05,254.00 was paid by the appellant to the respondent in full compliance to the award which included the interest quotient as well. No further amount remains to be paid. Therefore, the executing court rightly closed the execution case.
[2025] 9 S.C.R. 1385HLV Limited (Formerly Known as Hotel Leelaventure Pvt. Ltd.) v. PBSAMP Projects Pvt. Ltd.
14.4. It is submitted that respondent in its claim before the arbitral tribunal had itself calculated the interest portion at the rate of 21% simple interest from the date the payment became due till actual payment. As such, it is impermissible for the respondent to now turn around and claim compound interest i.e. post-award interest over and above the 21% interest agreed upon by the parties and awarded by the arbitral tribunal. Such claim virtually amounts to modification of the award which is impermissible at the stage of execution.
14.5. It is also submitted that Section 31(7)(a) and Section 31(7)(b) of the 1996 Act has no application to the facts of the present case as the arbitral tribunal itself awarded composite interest covering the entire period from the time the cause of action arose till payment. Arbitral tribunal did not award any postaward interest. Therefore, the decision of this Court in Hyder Consulting (UK) Limited (supra) would have no application.
14.6. Placing reliance on a subsequent decision of this Court in Morgan Securities and Credits Private Limited Vs. Videocon Industries Limited 2, learned senior counsel submits that this judgment has clarified the proposition laid down in Hyder Consulting (supra) by holding that an arbitral tribunal has the discretion to grant post-award interest either on the whole ‘sum’ or part of it. The decision in Hyder Consulting (supra) would only be applicable when the award is silent about payment of interest and not when the award clearly spells the method of paying interest including future interest. In fact, Morgan Securities (supra) has clarified the law laid down in Hyder Consulting (supra) by holding that when the award specifies the method of paying future interest, then Hyder Consulting (supra) would have no application. Therefore, the High Court clearly fell in error when it held that Morgan Securities (supra) would not apply to the facts of the case and remanding the matter back to the executing court for fresh decision placing reliance on Hyder Consulting (supra).
14.7. Learned senior counsel finally submits that High Court was not justified in summarily dismissing the order of the executing court as passed in a cryptic and cavalier manner.
2 (2023) 1 SCC 602
1386 [2025] 9 S.C.R.Supreme Court Reports
14.8. He, therefore, submits that view taken by the High Court is not correct. The same is required to be set aside and quashed. Consequently, the appeal should be allowed by restoring the order of the executing court.
15. Per contra, Mr. P.B. Suresh, learned senior counsel for the respondent submits that the impugned order does not determine any inter se rights of the parties. It is only an order of remand with the observation that the High Court has not expressed any opinion on merit. Therefore, such an order calls for no interference, that too, under Article 136 of the Constitution of India.
15.1. As and when the executing court decides the issue finally, parties to the lis would have the right to take recourse to the remedy as provided under the law. In such circumstances, filing of the special leave petition by the appellant is clearly an abuse of the process of the court.
15.2. As per the interest calculation sheet as on 31.07.2023 filed by the respondent before the executing court, appellant was liable to pay Rs. 57,74,68,490.00. As against this, appellant has only paid to the respondent Rs. 44,42,05,254.00 till 31.07.2023. Therefore, an amount of more than Rs. 13 crores still remains outstanding. It is required to be paid by the appellant to the respondent.
15.3. Learned senior counsel for the respondent submits that the interest for the prior period till the date of the award has to be capitalized which will then be the ‘sum’ in terms of Section 31(7)(a) of the 1996 Act. On that basis, the judgment debtor is entitled to 21% post-award interest on the above ‘sum’ till the date of payment. In addition to placing reliance on the decision of this Court in Hyder Consulting (supra), learned senior counsel submits that the issue raised by the respondent is no longer res integra. The decision in Hyder Consulting has since been explained and reiterated by this Court in North Delhi Municipal Corporation Vs. S.A. Builders Limited 3. As per the said judgment, respondent is entitled to compound interest under Section 31(7)(b) of the 1996 Act on the ‘sum’ determined in terms of Section 31(7)(a) of the said Act.
3 (2025) 7 SCC 132
[2025] 9 S.C.R. 1387HLV Limited (Formerly Known as Hotel Leelaventure Pvt. Ltd.) v. PBSAMP Projects Pvt. Ltd.
15.4. He finally submits that the civil appeal is devoid of any merit and is, as such, liable to be dismissed.
16. Submissions made by learned counsel for the parties have received the due consideration of the Court.
17. At the outset, let us examine Section 31(7) of the 1996 Act which at the relevant point of time read thus:
31. Form and contents of arbitral award.
(7)(a) Unless otherwise agreed by the parties, where and insofar as an arbitral award is for the payment of money, the Arbitral Tribunal may include in the sum for which the award is made interest, at such rate as it deems reasonable, on the whole or any part of the money, for the whole or any part of the period between the date on which the cause of action arose and the date on which the award is made.
(b) A sum directed to be paid by an arbitral award shall, unless the award otherwise directs, carry interest at the rate of eighteen per centum per annum from the date of the award to the date of payment.
17.1. From a perusal of the aforesaid provision, it is seen that Section 31(7) has got two clauses: clause (a) and clause (b). Clause (a) starts with the expression ‘unless otherwise agreed by the parties’. Thereafter, it says that where an award is for payment of money, the arbitral tribunal may include in the sum for which the award is made interest at such rate as it deems reasonable on the whole or any part of the money and for the whole or any part of the period from the date when the cause of action arose to the date when the award is made. In other words, clause (a) empowers the tribunal to include interest in the ‘sum’ for which the award is made. The arbitral tribunal is further conferred the discretion to award interest on the principal sum awarded at such rate as it deems reasonable. However, this discretion of the arbitral tribunal is subject to any decision which is agreed upon by the parties.
18. Clause (a) of Section 31(7) of the 1996 Act was examined by this Court in S.A. Builders (supra) whereafter it was held as under: 1388 [2025] 9 S.C.R.Supreme Court Reports
36.1. From a minute reading of sub-section (7), it is seen that it has got two parts: the first part i.e. clause
(a) deals with passing of award which would include interest up to the date on which the award is made. The second part i.e. clause (b) deals with grant of interest on the “sum” awarded by the Arbitral Tribunal.
36.2. Let us now discuss in detail the contours of the two clauses. As per clause (a), when an award is made by the Arbitral Tribunal for payment of money, the “sum” which is awarded may include interest at such rate as the Arbitral Tribunal deems appropriate, on the whole or any part of the money and for the whole or any part of the period. The period for which the interest may be granted would be between the date on which the cause of action arose and the date on which the award is made. The expression which needs to be noticed in this part is the following: the Arbitral Tribunal may include in the sum for which the award is made interest at such rate as it deems reasonable.
36.3. The word “may” appearing in the above expression is quite significant. It implies that the Arbitral Tribunal has the discretion to grant interest at a reasonable rate. In other words, it may grant interest or it may not grant interest; but if it grants interest, it would be included in the “sum” which is awarded by the Arbitral Tribunal.
19. Insofar clause (b), as it stood at the relevant time is concerned, it provides for award of interest by the arbitral tribunal on the ‘sum’ adjudged under clause (a). It says that ‘unless the award otherwise directs’, a sum directed to be paid by an award shall carry interest at the rate of 18% per annum from the date of the award to the date of payment. In other words, clause (b) is subject to the interest that may be awarded by the arbitral tribunal. This provision was explained in S.A. Builders (supra) in the following manner:
36.4. This brings us to the second part i.e. clause (b) which deals with post-award interest. The “sum” directed to be paid by the Arbitral Tribunal shall, unless the award otherwise directs, carry interest @ 18% p.a. from the date [2025] 9 S.C.R. 1389HLV Limited (Formerly Known as Hotel Leelaventure Pvt. Ltd.) v. PBSAMP Projects Pvt. Ltd.