Not a certified copy. Text extracted from the judgment PDF published by the Supreme Court of India. Verify against the certified copy before relying on it. Source: Supreme Court of India, via the Indian Supreme Court Judgments dataset by Dattam Labs (CC-BY-4.0). Retrieved 17 Nov 2026, 12:21 am. Original source ↗
Preview: first 50% of the document.
[2025] 12 S.C.R. 417 : 2025 INSC 1388 The State of Jharkhand v.
The Indian Builders Jamshedpur (Civil Appeal No(s). 8261-8262 of 2012)
05 December 2025 [Pamidighantam Sri Narasimha and Atul S. Chandurkar, JJ.] Issue for Consideration Bharat Drilling & Foundation Treatment Pvt. Ltd. v. State of Jharkhand and Ors. (2009) 16 SCC 705, if requires to be referred to a larger bench for reconsideration and authoritative decision in order to obviate uncertainty and for clear declaration of law as regards applicability of prohibited claims in a contract. Headnotes† Arbitration and Conciliation Act, 1996 – Arbitral Tribunal allowed certain claims of the respondent-claimant but the Civil Court set aside the claims 3, 4 and 6 on the ground that they were specifically prohibited under the contract between the parties – Appeal filed by the respondent, allowed by the High Court on the ground that the issue arising for consideration is covered by decision of this Court in Bharat Drilling and thus, allowed the claims barred under the contract restoring the arbitratal award – Challenge to – Plea of the State that the decision in Bharat Drilling is being applied, regularly and wrongly, to interpret prohibitory claim clauses in all Government contracts and thus, there is a compelling necessity to clarify the position of law: Held: Bharat Drilling is not an authority for the proposition that an excepted clause or a prohibited claim in a contract applies only to the employer and not to the Arbitral Tribunal – High Court did not examine the contractual clauses and proceeded to dispose of the appeal under the impression that the issue is conclusively covered by the decision of this Court in Bharat Drilling – In Bharat Drilling, the Court has not examined the contractual clauses that have fallen for consideration herein – Contractual clauses that limit claims are founded on freedom to contract – They are agreements that crystalise informed choices of parties – Applicability of excepted or prohibitory clauses would primarily depend upon the agreement between the parties, which alone is the guiding principle for the 418 [2025] 12 S.C.R.Supreme Court Reports Arbitral Tribunal – The judgment in Bharat Drilling, relying on the judgment of this Court in Port of Calcutta, dealing with the principle of grant of interest pendente lite, is not appropriate – Further, the approach adopted in Bharat Drilling is not in tune with the principles laid down by this Court in the recent decisions of Cox and Kings Ltd. v. SAP India Private Ltd. CORE and In Re: Interplay Between Arbitration Agreements Under Arbitration and Conciliation Act, 1996 and Stamp Act, 1899 – In order to ensure clarity and consistency, the ratio of Bharat Drilling requires to be reconsidered – Bharat Drilling referred to a larger bench for reconsideration and authoritative decision – Registry to place the present judgment and order before the Hon’ble Chief Justice for appropriate orders for placing the matter before a larger bench of appropriate strength. [Paras 1, 8, 9, 11] Case Law Cited Bharat Drilling & Foundation Treatment Pvt. Ltd. v. State of Jharkhand and Ors. (2009) 16 SCC 705 – requires to be reconsidered.
Board of Trustees For The Port of Calcutta v. Engineers-De- Space-Age [1995] Supp. 6 SCR 327 : (1996) 1 SCC 516; Central Organisation for Railway Electrification (CORE), 2024 INSC 857 : [2024] 11 SCR 2173 : 2024 SCC OnLine SC 3219; Pam Developments Private Limited v. State of West Bengal [2024] 8 SCR 615 : (2024) 10 SCC 715; Cox and Kings Ltd. v. SAP India Private Ltd. [2023] 15 SCR 621 : (2024) 4 SCC 1; Interplay Between Arbitration Agreements Under Arbitration and Conciliation Act, 1996 and Stamp Act, 1899 [2023] 15 SCR 1081 : 2023 SCC OnLine SC 1666 – referred to.
List of Keywords Excepted clause; Prohibited claim in a contract; Prohibitory clauses; Claims barred under the contract; Bharat Drilling referred to a larger bench for reconsideration.
Case Arising From CIVIL APPELLATE JURISDICTION: Civil Appeal No(s). 8261-8262 of 2012 From the Judgment and Order dated 11.05.2012 of The High Court of Jharkhand at Ranchi in AA No. 17 of 2007 and AA No. 24 of 2007 [2025] 12 S.C.R. 419The State of Jharkhand v. The Indian Builders Jamshedpur Appearances for Parties Advs. for the Appellant(s):
Rajiv Shankar Dwivedi, Ms. Tulika Mukherjee, Beenu Sharma, Venkat Narayan.
Adv. for the Respondent(s):
Manoj C. Mishra.
Judgment / Order of the Supreme Court Judgment
1. In view of our opinion that Bharat Drilling & Foundation Treatment Pvt. Ltd. v. State of Jharkhand and Ors1 is not an authority for the proposition that an excepted clause or a prohibited claim in a contract applies only to the employer and not to the Arbitral Tribunal, for the reasons to follow, in order to obviate uncertainty and for clear declaration of law, we are referring Bharat Drilling (supra) to a larger bench for reconsideration and authoritative decision. The context in which we have referred the matter to a larger bench is as follows.
2. State of Jharkhand is in appeal against the judgment of the High Court of Jharkhand allowing Section 372 appeal under Arbitration and Conciliation Act, 1996 3 . The appeal was filed by the respondentclaimant against the judgment of the Civil Court 4 setting aside the arbitral award allowing the objections filed by State under Section 34. By its award dated 19.04.2007, the Arbitral Tribunal allowed certain claims but the Civil Court set aside the claims 3, 4 and 6 on the ground that they were specifically prohibited under the contract between the parties.
3. Mr. Rajiv Shankar Dwivedi, learned counsel appearing for the State of Jharkhand has made a short submission that the High Court committed a serious error in allowing the appeal on the ground that the issue arising for consideration is covered by decision of this Court in Bharat Drilling (supra). Mr. Dwivedi has expressed a serious
1 (2009) 16 SCC 705.
2 In Arbitration Appeal No. 17 of 2007 dated 11.05.2012. 3 Hereinafter referred to as the ‘Act’.
4 Sub-Judge-1, Jamshedpur in Misc. Arbitration Case No. 01/2004 dated 19.04.2007. 420 [2025] 12 S.C.R.Supreme Court Reports concern that the decision in Bharat Drilling (supra) is being applied, regularly and wrongly, to interpret prohibitory claim clauses in all Government contracts. He would therefore submit that even if the Court may not interfere in the facts of this case, there is a compelling necessity to clarify the position of law. On the other hand, Mr. Manoj C. Mishra, learned counsel appearing for the respondent, supported the decision of the High Court.
4. In view of the concern expressed by Mr. Dwivedi, we agreed to examine the question of law and the principle in Bharat Drilling (supra). Before we proceed any further, it is necessary to examine the relevant clauses under the agreement, which are extracted hereinbelow for ready reference;
“4.20.0 CLAIMS:
4.20.2: No claim for idle labour, idle machinery, etc. on any account will be entertained… 4.20.4: No claim shall be entertained for business loss or any such loss.”
5. It is submitted that the Arbitral Tribunal committed a serious error in allowing claim no. 3 (relating to underutilised overheads) when that claim is barred under clause 4.20.2, claim no. 4 (relating to loss due to underutilised tools, plants and machinery) when such claim is clearly barred under contractual clause 4.20.2. Further, it is also contended that claim no. 6 (relating to loss of profit) could not have been granted in the teeth of clause 4.20.4, which specifically declares that “no claim shall be entertained for business loss or any such loss”.
6. This submission, however, found favour with the Civil Court accepting Section 34 objections of the State and setting aside the award on claim nos. 3, 4 and 6. When we peruse the judgment of the High Court under Section 37, we find that there is no discussion whatsoever as regards to claim nos. 3, 4 and 6, except for reference and reliance on the order of this Court in Bharat Drilling (supra). Placing reliance upon Bharat Drilling (supra), without any other discussion or analysis, the High Court proceeded to restore the award as regards claim nos.3, 4 and 6.
7. As we examined the decision of this Court in Bharat Drilling (supra), we find that it was argued therein that, the contractual “bar against such claims is applied only to the department and not to [2025] 12 S.C.R. 421The State of Jharkhand v. The Indian Builders Jamshedpur the Arbitral Tribunal”. Without examining the contention in detail, the Court proceeded further and referred to the decision of Board of Trustees For The Port of Calcutta v. Engineers-De-Space-Age5 and set aside the order passed by the High Court and restored the award. Mr. Dwivedi therefore contends that Bharat Drilling (supra) does not lay down any law and that it is an order in the facts and circumstances of the case.
8. It is quite evident from the order impugned before us that the High Court has not examined the contractual clauses extracted hereinabove and has proceeded to dispose of the appeal under the impression that the issue is conclusively covered by the decision of this Court in Bharat Drilling (supra). As has been already indicated, in Bharat Drilling (supra), the Court has not examined the contractual clauses that have fallen for our consideration herein. Contractual clauses that limit claims are founded on freedom to contract. They are agreements that crystalise informed choices of parties. Explaining the incorporation of party autonomy in the statutory scheme of the Act, this Court in Central Organisation for Railway Electrification (CORE),6 explained this position: