Arun Kumar Sharma & Ors. v. State of Madhya Pradesh & Ors.
- Citation
- 2025 INSC 826; [2025] 7 S.C.R. 593
- Court
- Supreme Court of India
- Bench
- 2 Judges: Justice Pamidighantam Sri Narasimha, Justice Joymalya Bagchi
- Decided
- 14 Jul 2025
- Case number
- CIVIL APPEAL No. 3263/2025
- Sections
- 14, 25, 21, 172
Not a certified copy. Text extracted from the judgment PDF published by the Supreme Court of India. Verify against the certified copy before relying on it. Source: Supreme Court of India, via the Indian Supreme Court Judgments dataset by Dattam Labs (CC-BY-4.0). Retrieved 17 Nov 2026, 12:19 am. Original source ↗
Preview: first 50% of the document.
[2025] 7 S.C.R. 593 : 2025 INSC 826 Arun Kumar Sharma & Ors.
v.
State of Madhya Pradesh & Ors.
(Civil Appeal No(s). 3263-3264 of 2025)
14 July 2025 [Pamidighantam Sri Narasimha* and Joymalya Bagchi, JJ.] Issue for Consideration Issue arose as regards the objections raised by the respondents about the bonafides of the appellants as also the allegations that the appellants suppressed the initiation of parallel proceedings before the High Court.
Headnotes† Practice and Procedure – Parallel proceedings – Nondisclosure – Application by the appellant for restraining respondents from setting up a petrol pump, as also challenged the NOC issued by the Collector – Application as also review petition dismissed by the tribunal – Appeal before this Court – Objections by the respondents that the appellants have suppressed the initiation of parallel proceedings before the High Court – Scope of proceedings before the tribunal and the High Court – Determination:
Held: Having considered the grounds and relief sought in the original application filed before the tribunal and having contrasted it with the grounds and prayers in the writ petition filed subsequently, when the present civil appeals were pending, it is clearly discernible from the pleadings that there is an overlap and parallel challenges to the same NOC – Appellants suppressed the necessary facts and there is reason to believe that the proceedings before tribunal were initiated to subserve business interest of the appellants – Even assuming that the scope and ambit of challenge is distinct, which they are not, the appellants could have done and infact should have informed this Court about initiation of the fresh proceeding challenging the NOC before the High Court, particularly when the civil appeals are pending consideration – Appeals dismissed with costs of Rs.50,000/- imposed on the appellants. [Paras 19, 21] * Author 594 [2025] 7 S.C.R.Supreme Court Reports List of Acts National Green Tribunal Act, 2010; Petroleum Rules, 2002; M.P. Nagar Tatha Gram Nivesh Adhiniyam, 1973; Water (Prevention and Control of Pollution) Act, 1974; Air (Prevention and Control of Pollution) Act, 1981.
List of Keywords Non-disclosure of parallel proceedings; Bonafides of appellants; Scope of proceedings; Overlap and parallel challenges; Petrol pump; Subserve business interest; Municipal laws; Cost. Case Arising From CIVIL APPELLATE JURISDICTION: Civil Appeal No(s). 3263-3264 of 2025 From the Judgment and Order dated 09.08.2024 and 17.10.2024 of the National Green Tribunal, Central Zonal Bench, Bhopal in OA No. 73 of 2024 and RA No. 8 of 2024, respectively Appearances for Parties Advs. for the Appellant:
Mrs. V. Mohana, Sr. Adv., Abhijit Banerjee, Ms. Sreepriya K. Advs. for the Respondents:
V.v.m.b.n.s. Pattabhiram, D.A.G., Pinaki Mishra, Anoop George Chaudhari, June Chaudhari, Sr. Advs., Sarad Kumar Singhania, Ms. Alpana Sharma, Raghav Sharma, Salvador Santosh Rebello, Jaskirat Pal Singh, Pranjal Pandey, Ms. Kritika, Parimal Bhatia, K. R. Sasiprabhu, Vishnu Sharma A S, Ms. Namrata Saraogi, Vikas Sharma, Vipin Nair, Mohd Aman Alam, Aditya Narendranath, Ms. M.b.ramya, Ms. Deeksha Gupta.
Judgment / Order of the Supreme Court Judgment Pamidighantam Sri Narasimha, J.
1. Access to justice is inextricably connected to maintaining integrity in the process of invocation and conduct of remedial proceedings before Courts and Tribunals. We have entertained these civil appeals [2025] 7 S.C.R. 595Arun Kumar Sharma & Ors. v. State of Madhya Pradesh & Ors. after sufficient warning that, in the event we accept the objections of the respondent about the deliberate non-disclosure of parallel proceedings initiated before the High Court, and that the original application before the Tribunal is not bonafide as it is intended to subserve personal interest of appellant no. 3, conducting rival business, these civil appeals will be dismissed with exemplary costs. This approach is necessary to ensure earnest and bonafide actions before the tribunals for protecting environment and ecology.
2. Short Facts and Prayer before the Tribunal: The short facts leading to filing of the present appeals are that the three appellants approached the National Green Tribunal 1 invoking Section 14 of the NGT Act for restraining respondents 4, 5 and 6 from setting up a Petrol Pump at Khasra No. 109/1/2 (S) situated on SH 10 Bhopal to Berasia road, Village- Intkhedi Road, Tehsil-Huzur, District-Bhopal. The prayers made in the original application are as follows:
“7. PRAYER In view of the aforesaid facts and circumstances as explained herein above, it is most respectfully prayed that Hon’ble Tribunal may graciously be pleased to allow the present Application and 7.1 Quash the Consent letter dated 19.07.2023; and 7.2 Quash the No-Objection Letter dated 07.02.2024 issued by Respondent No. 3; and 7.3 Direct the Respondents not to establish petrol pump within the proximity of designated residential area. 7.4 Allow the Applicant to add, delete, modify, substitute, amend the present Application and submit additional documents, if occasion so arises; and 7.5 Cost of the matter may also be awarded;
7.6 Till the pendency of the present matter ad interim relief by way of restraining the Respondent No. 4 & 5 to stop construction of petrol pump activities may also be granted in the interest of justice.
1 Hereinafter referred to as ‘NGT’.
596 [2025] 7 S.C.R.Supreme Court Reports 7.7 Any other relief, which Hon’ble Tribunal may deem just and proper may also be awarded in favour of the Applicant as against the Respondents.”
3. It is clear from the above referred prayers that the appellants have specifically challenged, (i) the consent to operate dated 19.07.2023 issued by the Madhya Pradesh Pollution Control Board Bhopal under the Water (Prevention and Control of Pollution) Act, 1974 and the Air (Prevention and Control of Pollution) Act, 1981 and (ii) the NOC dated 07.02.2024 issued by the Collector enabling installation of the petrol pump retail outlet as per the application made by the contesting respondents.
4. Apart from other grounds, the decision of District Collector dated 07.02.2024 is challenged on the ground that he has not applied his mind while issuing the said NOC and that it is contrary to the Petroleum Rules, 2002. The relevant grounds of challenge are as follows:
“4.17 However, the Respondent No. 3, without looking into various aspects, issued No-Objection Certificate to the Respondent no. 4 & 5 vide NOC dated 07.02.2024.
4.18. It is submitted that the Applicant vide Notice dated 24.12.2023 & 13.02.2024 to the Respondents requested to stay the illegal construction by the Respondent No. 4 & 5 for establishment of petrol pump at the Said Land, citing the various environmental issues.
4.19. In the letter dated 24.12.2023 & 13.02.2024, the Applicant raised the issues that the Respondent No. 3 is required to issue No-Objection Certificate in accordance with the Rule 144 of the Petroleum Rules, 2002, in the prescribed proforma. The Rule 144 prescribes the District Authority, i.e. the Respondent No. 3 to issue license if there is no objections to the Applicant receiving a license for the site proposed. Further, the District Authority is also required to protect the interest of public, especially facility like schools, hospitals or proximity to places.
4.20. Now, the Respondent No. 4 & 5 are establishing petrol pump at the Said Land in sheer violation of Hon’ble NGT Orders, CPCB Guidelines and PESO Guidelines.
[2025] 7 S.C.R. 597Arun Kumar Sharma & Ors. v. State of Madhya Pradesh & Ors.
4.21. That establishment of petrol pump in a residential area poses multifaceted risks and hazards, both to the environment and to the health and safety of the residents. The CPCB Guidelines clearly stipulate the minimum distance requirements for setting up petrol pumps from residential areas, school, hospitals, and other sensitive establishments. It is evident that the Said Land fails to comply with these crucial safety regulations, thereby jeopardizing the lives and well-being of the residents.
4.22. Furthermore, the establishment of a petrol pump in close proximity to designated residential area raises serious concerns regarding air, water and noise pollution. The operation of fuel dispensing units, vehicular traffic, and other associated activities are known to emit harmful pollutants, including volatile organic compounds (VOCs), particulate matter, and noise, which can have detrimental effects on both the environment and public health.
4.23. Additionally, CPCB guidelines and NGT Orders, which aim to mitigate the adverse environmental impacts associated with fuel retailing activities. Failure to adhere to these guidelines not only undermines the regulatory framework put in place to safeguard the environment but also sets a dangerous precedent for füture development projects.
4.24. Considering the gravity of the situation and the potential ramifications for the environment and public health, by way of the present Application, the Applicant urge the Hon’ble National Green Tribunal to intervene expeditiously and cancel the NOC Issued by the Respondent No. 3 and Consent letter issued by Respondent No. 1 to prevent the establishment of the Respondent no. 4 & 5 petrol pump in the designated residential area and school. In the present Application, the Applicant is only bringing the environmental issues for adjudication before the Hon’ble NGT. For other procedural and substantial illegalities being committed by the Respondents, the Applicant reserves its right to approach appropriate forum, at appropriate stage.” 598 [2025] 7 S.C.R.Supreme Court Reports
5. While issuing notice on 21.03.2024, the NGT constituted a Joint Committee and directed it to submit a factual report within six weeks.
6. Various permissions already obtained by the respondents: Pending enquiry and report from the Joint Committee, the contesting respondents 4, 5 and 6 filed a detailed counter affidavit as per which the following permissions have already been obtained.
(i) Firstly, on 30.04.2024, the Ministry of Petroleum and Explosives Safety Organization (PESO) granted NOC in favour of Reliance BP Mobility Ltd.
(ii) Secondly, on 26.04.2023, the CEO of Janpad Panchayat Phanda, Bhopal, M.P. issued NOC
(iii) Thirdly, Madhya Pradesh Road Development Corporation also issued NOC on 26.05.2023
(iv) Fourthly, on 26.04.2023, Madhya Pradesh Electricity Board also issued NOC
(v) Fifthly, on 10.04.2023, the Industrial Department also issued its NOC
(vi) Sixthly, on 19.07.2023, the Madhya Pradesh Pollution Control Board issued its consent to operate under the Water and Air Act, and
(vii) Finally, on 07.02.2024, the Collector also issued the NOC in favour of the contested respondent.
7. It is an admitted fact that all the above referred NOCs as well as the consent to operate were issued prior to the filing of the original application before the NGT on 15.03.2024.
8. Findings of the Joint Committee constituted by NGT: The Joint Committee submitted its report on 09.07.2024. The procedure adopted for conducting the enquiry, the field observations, information provided by the Revenue Department and the Pollution Control Board, along with the findings, are extracted herein below for ready reference. “4. Field Observations: -
4.1. Joint committee on dated 07/06/2024 conducted a site visit of Khasra No. 109/1/20 (S) stiuated on SH 10 Bhopal to Berasia road, Village- Intkhedi Road, Tehsil-Huzur, [2025] 7 S.C.R. 599Arun Kumar Sharma & Ors. v. State of Madhya Pradesh & Ors. District-Bhopal. Apart from the Joint Committee members following officers namely Ms. Prakamya Tiwari, AE, RO, MPPCB, Bhopal, Shri Kanak Meena, Deputy Controller, PESO, Bhopal and Shri Kailash Sharwa, Patwari, Halka- Intkhedi Sadak, Gram Panchayat-Intkhedi Sadak were also present during the site visit. The Advocate of petitioner Shri Prateek Jain was informed by the nodal department about the visit of committee and he was present during the visit. Also, the representative of petrol pump Shri Aman Ahmed Khan was present. The Geographical locations, photographs and visual observations were recorded during inspection. The Photographs and Google Maps are enclosed as Annexure I.
4.2. During inspection, Joint Committee visited the site of Petrol Pump mentioned in the petition. The details observed during the inspection are mentioned as under: - 4.2.1. The site is located on SH 10, Intkhedi Road, Village-Intkhedi Road, Tehsil-Huzur, District-Bhopal. The geographical location of the site is latitude 23°22’20.95” N and longitude 77º23’58.41 E”.
4.2.2. The SH 10 road is situated on the East of the petrol pump. The New Government Higher Secondary School is located at a distance of approximately 120 meters away to the South-West of the petrol pump.
4.2.3. On north side of the petrol pump there are some commercial establishments located at a distance of approximately 30 meters away, the north of the petrol pump. 4.2.4. On south side of the petrol pump there are some commercial buildings, incomplete building structures named as Maruti Udyog, one cement shop, steel TMT bar Shop as per the sign boards placed on the shops, which are located at a distance of approximately 30 meters away. 4.2.5. The primary development work for the establishment of Petrol Pump was found in progress.
4.2.6. The residential colonies as mentioned in the petition are located on the west side of the petrol pump.
600 [2025] 7 S.C.R.Supreme Court Reports 4.2.7. The distance from the dispensing unit to the boundary of the Petrol pump towards residential colonies on west side is approx. 38 meters.
4.2.8. During visit of the Joint Committee, no residential houses were found constructed in the above residential colonies and no habitation were observed.
4.2.9. No high tension line was found passing through the petrol pump site.
5. Information provided by the Revenue Department, Tehsil-Huzur, Bhopal
5.1. Letter vide dated 19/06/2024 was issued by MPPCB (Nodal Department) to SDM, Tehsil-Huzur to provide the information of permissions / locations of Petrol Pump, School, Hospital and Residential colony within 50 meter distance from the Petrol Pump as per revenue records. The copy is enclosed as Annexure Il.
5.2. SDM, Tehsil-Huzur, Bhopal vide letter dated 03/07/2024 provided the information. The copy of the letter is enclosed as Annexure III. The main points of the letter are mentioned as under:- No Main Points As per Revenue Record 1 Petrol Pump is proposed on Khasra No. 109/1/2 located at Village-Intekhedi Road, Tehsil-Huzur, District-Bhopal.
The Petrol Pump is located on part of Khasra no. 109/1/2 and on Khasra no. 109/1/2 Vi l l a g e - I n t e k h e d i R o a d Tehsil-Huzur, District-Bhopal of area 0.19 hectares, which is registered for commercial purpose in the name of Aman Ahmed Khan S/o Jameel Ahmed Khan.
2 The residential colonies respectively Anjani Nandan Dham and Ramnagar are established for residential purpose at Khasra No. 108, 109/2 and 109/1/1 near the site (Petrol Pump), The residential colonies respectively Anjani Nandan D h a m a n d R a m n a g a r established at Khasra No.
108, 109/2 and 109/1/1 are Unauthorised residential colonies.
[2025] 7 S.C.R. 601Arun Kumar Sharma & Ors. v. State of Madhya Pradesh & Ors. 3 G o v e r n m e n t H i g h e r Secondary School is located 50 meters from the petrol pump and a hospital is also located nearby.
No Hospital or Government/ private school located within a periphery of 50 meters from the petrol pump and there is no residential activity within a periphery of 50 meters from the fuel section of the petrol pump is operated.
4 Information of the designated residential area, school and hospital located around the said petrol pump.
The designated residential area, school and hospital are not within the periphery of 50 meters from Petrol Pump.
The traditional settlement/ population of Village-Intkhedi Road is 600 meters away from the under construction Petrol Pump.
6. Information of MPPCB:- 6.1 As per the application submitted by Project proponent of Petrol Pump for establishing a Petrol Pump, MPPCB vide outward No:24612 dated 19/07/2023 issued Consent to Establish under Section 25 of the Water (Prevention & Control of Pollution) Act, 1974 and Section 21 of the Air (Prevention & Control of Pollution) Act, 1981. The copy is enclosed as Annexure IV 6.2 The Consent to Establish was issued with the conditions that new petrol pump should be at least 50 meters away from school, hospital and residential areas. If Petrol pump located within 50 meters radius of any school, hospital and residential complex it must obey provisions of Petroleum Rules, 2002, administered by Petroleum and Explosive safety organization. No high-tension wire should be passed through outlet.
7. Findings of the Joint Committee:- 7.1 The committee finds that the residential colonies near the petrol pump as mentioned in the petition are unauthorized residential colonies and as per the record of Revenue department there is no designated residential colony within 50 meters distance from dispensing unit of petrol pump. 602 [2025] 7 S.C.R.Supreme Court Reports 7.2 It is also found that there are no schools or hospitals exist within 50 meters distance from the petrol pump. 7.3 The nearest habitation of people around the Village is 600 meters away from the Petrol Pump that is under construction at Village- Intkhedi road.
Continue reading
Sign in and become a member to continue reading this judgment and every other document in the library.