Municipal Corporation of Delhi v. Gagan Narang & Ors. Etc.
- Citation
- 2025 INSC 2; [2025] 1 S.C.R. 239
- Court
- Supreme Court of India
- Bench
- 2 Judges: Justice Bhushan Ramkrishna Gavai, Justice K.V. Viswanathan
- Decided
- 1 Jan 2025
- Case number
- CIVIL APPEAL No. 7463/2023
- Sections
- 63, 2(41), 62, 86(1), 86, 125, 175, 79(1), 3, 11, 174, 173
Not a certified copy. Text extracted from the judgment PDF published by the Supreme Court of India. Verify against the certified copy before relying on it. Source: Supreme Court of India, via the Indian Supreme Court Judgments dataset by Dattam Labs (CC-BY-4.0). Retrieved 17 Nov 2026, 12:21 am. Original source ↗
Preview: first 50% of the document.
[2025] 1 S.C.R. 239 : 2025 INSC 2 Municipal Corporation of Delhi v.
Gagan Narang & Ors. Etc.
(Civil Appeal Nos. 7463-7464 of 2023)
02 January 2025 [B.R. Gavai* and K.V. Viswanathan, JJ.] Issue for Consideration Whether the application under Section 63 of the Electricity Act, 2003 could have been made by the Appellant-MCD, a “local authority” within the meaning of Section 2(41) of the Act.
Headnotes† Electricity Act, 2003 – ss.63, 86, 2(41), 174, 175 – Determination of tariff by bidding process – Functions of the State Commission – Solid Waste Management Rules, 2016 – r.15 – Appellant, if could issue tariff based bid and Request for Proposal (RfP) for setting up the Waste to Energy Project – Petition filed by appellant before the Delhi Electricity Regulatory Commission (DERC) for approval of the bidding process of the Project – Waste to Energy Research & Technology Council (WTERT) challenged the authority of the appellant to issue the tariff-based bid and the RfP in setting up the Project – DERC dismissed the petition of WTERT while allowed that of the appellant and approved the bid tariff of Rs.7.38/KWh for the project and directed the Distribution Licensee to negotiate the terms of the Power Purchase Agreement with the appellant – Orders of DERC set aside by APTEL holding that since the appellant was neither a distribution licensee nor a generating company, it had no jurisdiction to file an application u/s.63 for adoption of tariff – Challenge to:
Held: Impugned judgment quashed and set aside – Appellant was establishing the Project in order to perform its statutory obligations – DERC granted its approval to the tariff with certain conditions after taking into consideration all the relevant factors – However, the same was upset by APTEL on a hyper-technical ground – Under/s.63, the * Author 240 [2025] 1 S.C.R.Digital Supreme Court Reports Appropriate Commission is entitled to adopt the tariff if such tariff has been determined through a transparent process of bidding in accordance with the guidelines issued by the Central Government – Power of the Commission is notwithstanding anything contained in s.62 – A plain reading of s.63 shows that it does not restrict its invocation only by Discoms or generating companies – The interpretation of APTEL is adding words in s.63 which the legislature did not intend to – Further, APTEL could not have read s.63 in isolation – s.63 will have to be read in harmony with s.86(1)(b) – The legislature intended that the State Commission while exercising its powers u/s.63 shall adopt the tariff when it has been determined in the bidding process – However, while adopting the same it will have to be satisfied that the same is done in a transparent manner and as to whether the interests of the generators/Discoms are balanced with the interests of the consumers – Reading s.63 in the manner as interpreted by the APTEL, would impose unnecessary restrictions on the powers and duties of the State Commission u/s.86(1)(b) which are of a very wide amplitude – Furthermore, there is no inconsistency between the provisions of s.63 and r.15, SWM Rules – r.15 enacted under the Environment (Protection) Act, 1986, mandates the appellant to undertake WTE project – Insofar as the WTE projects are concerned, the provisions under the Act will have to be read in addition to the provisions u/r.15 and not in derogation thereof – Also, s.86(1)(e) r/w r.6.4 of the Tariff Policy provide for promoting cogeneration and generation of electricity from renewable sources of energy by providing suitable measures for connectivity with the grid and sale of electricity from such sources, a percentage of the total consumption of electricity in the area of a distribution licensee – APTEL also failed to take into consideration that the WTE project in question was in the larger public interest providing for disposal of the huge quantity of waste generated in the city of Delhi – Orders of DERC affirmed – Environment (Protection) Act, 1986. [Paras 28, 29, 35, 37, 41, 42, 48, 49, 50, 52, 54-56, 58] Interpretation of Statutes – Electricity Act, 2003 – s.63 – Interpretation of – Literal interpretation – Courts by judicial interpretation not to add, alter, or delete the words when the statute upon its plain reading is capable of giving a meaning as intended by the legislature:
Held: When the statute read in a literal manner is capable of giving meaning to the provision that the legislation intended to [2025] 1 S.C.R. 241Municipal Corporation of Delhi v. Gagan Narang & Ors. Etc and does not lead to any absurdity, it is not permissible by judicial interpretation to add, alter, or delete any words to such a statute – Upon a plain reading of the provisions of s.63, the meaning gathered does not result in any absurdity thus, addition of words in the statute by judicial interpretation is wholly impermissible. [Paras 30, 36] Electricity Act, 2003 – s.86 – Duty of the State Commission – Discussed.
Case Law Cited Pune Municipal Corporation v. Sus Road Baner Vikas Manch and others [2024] 9 SCR 374 : (2024) 9 SCC 1; Energy Watchdog v. Central Electricity Regulatory Commission and others [2017] 3 SCR 153 : (2017) 14 SCC 80; Punjab State Power Corporation Limited and another v. Emta Coal Limited [2021] 11 SCR 772 : (2022) 2 SCC 1; Jaipur Vidyut Vitran Nigam Limited and others v. MB Power (Madhya Pradesh) Limited and others [2024] 1 SCR 909 : (2024) 8 SCC 513; Sanjay Ramdas Patil v. Sanjay and others [2021] 11 SCR 640 : (2021) 10 SCC 306 – referred to. List of Acts Electricity Act, 2003; Solid Waste Management Rules, 2016; National Tariff Policy 2016; Environment (Protection) Act, 1986. List of Keywords Municipal Corporation of Delhi (MCD); “local authority”; Competitive bidding process; Determination of tariff; Bid tariff; Approval of tariff; Appropriate Commission; State Commission; Solid Waste Management; Statutory obligations; Notice Inviting Tender; Tariff based bid; Request for Proposal (RfP); Financial Bids; Transparent process of bidding; Waste to Energy Project at Narela Bawana, Delhi; WTE project; Procurement of power; Delhi Electricity Regulatory Commission (DERC); APTEL; Waste to Energy Research & Technology Council; Tariff Policy; Power Purchase Agreement (PPA); Distribution Companies; Distribution Licensee; Discoms or generating companies/generators; Cogeneration, generation of electricity; Sale of electricity; Electricity from renewable sources of energy; Bidding Evaluation Committee; Plain reading; Literal interpretation; Judicial interpretation; Harmonious construction.
242 [2025] 1 S.C.R.Digital Supreme Court Reports Case Arising From CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 7463-7464 of 2023 From the Judgment and Order dated 31.08.2023 of the Appellate Tribunal for Electricity at New Delhi in DFR Nos. 245 and 247 of 2023 Appearances for Parties Ramji Srinivasan, Sr. Adv., Ms. Swapna Seshadri, Nikunj Dayal, Utkarsh Singh, Ms. Sneha Singh Baghel, Ms. Namrata Saraogi, Parth Bhalla, Advs. for the Appellant.
B.V. Patil, Sr. Adv., Aditya Ranjan, Krishna M. Singh, Anil C Nishani, Mrs. Deepti Singh (for M/s. Krishna & Nishani Law Chambers), Ms. Ishita Jain, Anand Kumar Shrivastava, Ms. Priya Goyal, Ms. Eesha Sharma, Buddy Ranganathan, Dushyant Manocha, Ms. Anannya Ghosh, Brian Henry Moses, Ms. Mrinalini Mishra, Suresh Chandra Tripathy, Advs. for the Respondents.
Pukhrambam Ramesh Kumar, Ms. Molshree Bhatnaagar, Deepak Thukar, Punyam Bhutani, Advs. for the Impleader.
Judgment / Order of the Supreme Court Judgment B.R. Gavai, J.
1. The present appeals filed under Section 125 of the Electricity Act, 2003 1 arise out of the Impugned common final judgment and order of the Appellate Tribunal for Electricity at New Delhi 2 dated 31 st August 2023 passed in DFR No. 245 of 2023 and DFR No. 247 of 2023 which were both filed by the Respondent No. 1 herein- Mr. Gagan Narang. The APTEL disposed of the appeals and set aside the orders of the Delhi Electricity Regulatory Commission 3 dated 6th and 7 th March 2023. Vide the order dated 6 th March 2023 the DERC had dismissed the petition filed by Waste to Energy 1 ‘The Act’ hereinafter 2 ‘APTEL’ hereinafter 3 ‘DERC’ hereinafter [2025] 1 S.C.R. 243Municipal Corporation of Delhi v. Gagan Narang & Ors. Etc Research & Technology Council4 challenging the authority of the Appellant herein - Municipal Corporation of Delhi, 5 to issue the tariff-based bid and Request for Proposal 6 for setting up the Waste to Energy 7 project at Narela Bawana, Delhi. Vide order of 7 th March 2023, the DERC had approved the bid tariff of Rs. 7.38/KWh for the project and had directed the Distribution Licensee to negotiate the terms of the Power Purchase Agreement 8 with the Appellant-MCD.
2. Shorn of details, the facts leading to the present appeals are: 2.1 The Appellant-MCD organized a meeting with the Distribution Licensees in Delhi and other stakeholders on 14 th May 2022. It was agreed that a tariff-based bidding model may be adopted and the details about the same, including the volume of waste, total power generation, and other considerations for the proposed project were decided. It was further decided that the sale of power be distributed amongst the Distribution Licensees as per their ‘Renewable Purchase Obligation’. The Appellant was authorized to conduct the bidding process as per the regulations and requirements of Section 63 of the Act for the proposed WTE project. The same was put in writing and was detailed in the Minutes of Meeting dated 30th May 2022.
2.2 The Appellant-MCD, issued the Notice Inviting Tender 9 and the RfP dated 15 th July 2022 whereby the tariff-based bids for procurement of power under WTE project for Solid WTE Processing Facility with a minimum 28 MW capacity in Narela Bawana, New Delhi, for 3000 (+/- 20%) TPD of MSW 10 were invited. The documents for the same were sent to the DERC for its consideration.
2.3 The DERC, vide letter dated 24 th August 2022 directed the Appellant-MCD to file a petition for approval of PPA, RfP, etc. The letter also contained the details of the petitions filed by 4 ‘WTERT’ hereinafter 5 ‘Appellant-MCD’ hereinafter 6 ‘RfP’ hereinafter 7 ‘WTE’ hereinafter 8 ‘PPA’ hereinafter 9 ‘NIT’ hereinafter 10 ‘Project’ hereinafter 244 [2025] 1 S.C.R.Digital Supreme Court Reports South Delhi Municipal Corporation and the East Delhi Waste Processing Co. Ltd. seeking similar approvals, which were granted by the DERC through separate orders. An evaluation committee was also constituted for the evaluation of bids and other related issues. The Appellant-MCD issued a notice that the bidding process dated 15 th July 2022 were closed and a new NIT was issued on 21 st October 2022 with identical terms as the earlier NIT.
2.4 The WTERT filed a Petition No. 65 of 2022 before the DERC inter alia challenging the authority of the Appellant-MCD for issuing the tariff-based bid and the RfP in setting up the Project. During the pendency of this petition, the bidding process was undertaken, and on 14 th November 2022, bids were received from M/s JITF Urban Infrastructure Ltd. and M/s JBM Renewables Pvt. Ltd. A meeting of the Evaluation committee was held, and the documents submitted by the bidders keeping in mind the requirement of the RfP document were discussed, and on recommendation of the committee, the bids of both the bidders were declared to be technically qualified and their bids were allowed to be opened. The Regional Centre for Urban & Environmental Studies 11 calculated the levelized tariff based on the RfP and the same was communicated and calculated as: Name of the Bidder Levelized Tariff (Rs/KWh)
M/s JITF Urban Infrastructure Limited 7.380 M/s JBM Renewable Pvt. Limited 9.909 2.5 The Financial Bids were evaluated by the Evaluation Committee and its recommendation report dated 26th November 2022 was issued. It was stated in the report that in accordance with the terms of the RfP, the “Lowest Bidder” for a project was to be the qualified bidder and the lowest evaluated levelized tariff shall be the selected bidder for the Project. M/s JITF Urban Infrastructure Limited was selected to be the lowest bidder with a levelized tariff bid of Rs. 7.380/KWh. It was further mentioned that a meeting of the Evaluation Committee was held on 6th 11 ‘RCUES’ hereinafter [2025] 1 S.C.R. 245Municipal Corporation of Delhi v. Gagan Narang & Ors. Etc October 2022 for the consideration of the Financial Model for price bid evaluation prepared by RCUES. The representative of RCUES presented the financial model and after deliberation, the committee reached a consensus on the key assumptions taken and had arrived at a levelized tariff of Rs. 6.73/KWh. Since, there existed a difference between the tariff according to the financial model and the tariff by the lowest bidder, a justification/ calculation for arriving at the quoted bid was requested from M/s JITF Urban Infrastructure Limited, and the same was considered by the committee. It was further mentioned, that after detailed deliberations, the committee was of the opinion that the bids had been received through a competitive bidding process and the lowest bid of Rs. 7.380/KWh was arrived at, through a competitive and transparent bidding process. It was further mentioned that the Appellant-MCD herein has no benefit or loss accruing out of this as the power is to be procured by the Distribution Companies in accordance with the approval of tariff by DERC. The report was then forwarded to the DERC as the final approval was to be given by it.
2.6 Pursuant to the same, the Appellant-MCD filed a Petition No. 72 of 2022 before the DERC for the approval of the bidding process of the Project.
2.7 The DERC, vide order dated 6th March 2023, dismissed the Petition No. 65 filed by WTERT and inter alia held that the Appellant-MCD is mandated under the Solid Waste Management Rules, 201612 to construct, operate, and maintain the solid waste processing facilities. Vide order dated 7 th March 2023, the DERC in Petition No. 72 filed by the Appellant-MCD herein, approved the bid tariff of Rs. 7.38/KWh for the project and directed the Distribution Licensee to negotiate terms of the PPA with the Appellant-MCD and place a signed copy of the PPA before the DERC within three months.
2.8 Aggrieved, two separate appeals were filed by the Respondent No. 1 herein bearing DFR Nos. 245 of 2023 and 247 of 2023 against the orders dated 7 th March 2023 and 6 th March 2023 respectively.
12 ‘SWM Rule 2016’ hereinafter 246 [2025] 1 S.C.R.Digital Supreme Court Reports 2.9 The APTEL, vide the Impugned common final judgment and order dated 31st August 2023 disposed of the appeals and set aside both the orders dated 6 th and 7 th March 2023 passed by the DERC on the ground that the DERC lacked jurisdiction to entertain and adjudicate upon a petition filed by the Appellant- MCD herein.
2.10 Aggrieved, the present appeals are filed under Section 125 of the Electricity Act, 2003.
3. We have heard Mr. Ramji Srinivasan, learned Senior Counsel appearing for the Appellant and Mr. Basava Prabhu Patil, learned Senior Counsel appearing for the Respondent No.1, Mr. Krishna M. Singh, Ms. Ishita Jain, Mr. Buddy Ranganathan, Mr. Suresh Chandra Tripathi, learned counsel appearing for Respondent Nos. 2, 3, 4 & 5, and 9 respectively and Mr. Pukhrambam Ramesh Kumar, learned counsel for the applicant.
4. Mr. Ramji Srinivasan, learned Senior Counsel appearing for the Appellant submits that the APTEL has grossly erred in restricting the applicability of Sections 63 and 86(1)(b) of the Act only to the distribution licensee 13 or generating company insofar as the filing of application for adoption of tariff is concerned. He submits that the provisions of Section 86(1)(b) of the Act would reveal that a wide power is bestowed upon the State Commission to regulate electricity purchase and procurement process of Discoms including the price at which electricity shall be procured from the generating companies or licensees or from other sources.
5. Learned Senior Counsel further submits that the Appellant-MCD, which is a statutory body under the Delhi Municipal Corporation Act, has been put under statutory obligation under Rule 15(v)(b) of the SWM Rules 2016 to proceed for setting up of the WTE projects. It is submitted that this statutory duty has also been recognized by this Court in the case of Pune Municipal Corporation v. Sus Road Baner Vikas Manch and others.14
6. The learned Senior Counsel further submits that Rule 6.4(1)(ii) and (2) of the National Tariff Policy 2016 mandates Discoms to 13 ‘Discoms’ hereinafter 14 [2024] 9 SCR 374 : (2024) 9 SCC 1 [2025] 1 S.C.R. 247Municipal Corporation of Delhi v. Gagan Narang & Ors. Etc procure 100% of the power produced from all WTE plants either through Section 62 (normative tariff process) or through Section 63 (competitive based mechanism).
7. It is further submitted that Section 175 of the Act itself provides that the provisions of the Act are in addition to and not in derogation of any other law for the time being in force. It is, therefore, submitted that the mandate for setting up the WTE project by MCD has to be read in consonance with the provisions of the Environment (Protection) Act, 1986 and the Rules framed thereunder.
8. It is submitted that for WTE projects, no guidelines have been framed by the Central Government for conducting the bidding and accordingly the DERC has exercised its powers to regulate under Section 86(1)(b) of the Act to approve the bidding process and adopt the tariff. It is submitted that this is in tune with the judgment of this Court in the case of Energy Watchdog v. Central Electricity Regulatory Commission and others,15 wherein this Court has held that in a situation when there are no guidelines, then the general regulatory powers under Section 79(1)(b) can be exercised by the Commission. It is, therefore, submitted that by the same analogy the State Commission can exercise such powers in view of Section 86(1)(b) of the Act.
9. The learned Senior Counsel submits that the APTEL has failed to take into consideration the larger issue of public interest. It is submitted that WTE project was necessary for processing the unprocessed municipal solid waste which is increasing day by day.
10. It is further submitted that the DERC vide its order dated 6 th March 2023 had held that the Appellant-MCD under Rule 15(v) of the SWM Rules 2016 was performing its statutory functions to conduct the bidding process for the Project and that there is no bar in the National Tariff Policy that WTE project cannot be set up under Section 63 of the Act. It is submitted that on an earlier occasion also the DERC has approved the bidding process with regard to Tehkhand WTE at Okhla which is under operation and supplying electricity to all Delhi Discoms.
11. Mr. Basava Prabhu Patil, learned Senior Counsel appearing for the Respondent No.1, on the contrary, submits that the APTEL has 15 [2017] 3 SCR 153 : (2017) 14 SCC 80 248 [2025] 1 S.C.R.Digital Supreme Court Reports rightly held that the Appellant-MCD was not entitled to make an application for adoption of tariff under Section 63 of the Act. It is submitted that the APTEL rightly held that it is only the Discoms or generating companies who are entitled to invoke the provisions of Section 63 of the Act. The learned Senior Counsel submits that in view of Rule 6.4(2) of the National Tariff Policy, 2016, it is exclusively for the Ministry of Power to provide a mechanism for adoption of tariff for WTE projects. It is, therefore, submitted that the DERC has no jurisdiction to entertain the application filed by the present Appellant- MCD. He, therefore, prays for the dismissal of the present appeals.
12. The limited question that falls for consideration in the present appeals is that, whether the application under Section 63 of the Act could have been made by the present Appellant-MCD which is a “local authority” within the meaning of Section 2(41) of the Act.
13. For appreciating the rival controversy, it will be necessary to consider the nature of the Project which the Appellant-MCD was implementing. For the said purpose, it will be relevant to refer to clauses (q) and (v) of Rule 15 of the SWM Rules 2016, which read thus:
“15. Duties and responsibilities of local authorities and village panchayats of census towns and urban agglomerations.—The local authorities and Panchayats shall— ***
(q) transport segregated bio-degradable waste to the processing facilities like compost plant, biomethanation plant or any such facility. Preference shall be given for on site processing of such waste;
***
(v) facilitate construction, operation and maintenance of solid waste processing facilities and associated infrastructure on their own or with private sector participation or through any agency for optimum utilisation or various components of solid waste adopting suitable technology including the following technologies and adhering to the guidelines issued by the Ministry of Urban Development from time to time and standards prescribed by the Central [2025] 1 S.C.R. 249Municipal Corporation of Delhi v. Gagan Narang & Ors. Etc Pollution Control Board. Preference shall be given to decentralised processing to minimise transportation cost and environmental impacts such as—
(a) bio-methanation, microbial composting, vermicomposting, anaerobic digestion or any other appropriate processing for bio-stabilisation of biodegradable waste;
(b) waste to energy processes including refused derived fuel for combustible fraction of waste or supply as feedstock to solid waste based power plants or cement kilns;”
14. It could thus be seen that the SWM Rules 2016 require that, while making provisions for solid waste disposal, the authorities shall give a preference to decentralized processing to minimize transportation cost and environmental impacts such as, waste to energy processes including refused derived fuel for combustible fraction of waste or supply as feedstock to solid waste based power plants or cement kilns.
15. It is further to be noted that the “Tariff Policy” notified by the Ministry of Power on 28 th January 2016 is in compliance with the mandate of Section 3 of the Act. It could further be seen that under the said “Tariff Policy”, a provision has been made for renewable sources of energy generation including Co-generation from renewable energy sources. It will be relevant to refer to Rule 6.4 of the said “Tariff Policy”, which reads thus:
“6.4 Renewable sources of energy generation including Co-generation from renewable energy sources:
(1) Pursuant to provisions of section 86(1)(e) of the Act, the Appropriate Commission shall fix a minimum percentage of the total consumption of electricity in the area of a distribution licensee for purchase of energy from renewable energy sources, taking into account availability of such resources and its impact on retail tariffs. Cost of purchase of renewable energy shall be taken into account while determining tariff by SERCs. Long term growth trajectory of Renewable Purchase Obligations (RPOs) will be prescribed by the Ministry of Power in consultation with MNRE.
250 [2025] 1 S.C.R.Digital Supreme Court Reports Provided that cogeneration from sources other than renewable sources shall not be excluded from the applicability of RPOs.
(i) Within the percentage so made applicable, to start with, the SERCs shall also reserve a minimum percentage for purchase of solar energy from the date of notification of this policy which shall be such that it reaches 8% of total consumption of energy, excluding Hydro Power, by March 2022 or as notified by the Central Government from time to time.
(ii) Distribution Licensee(s) shall compulsorily procure 100% power produced from all the Waste-to-Energy plants in the State, in the ratio of their procurement of power from all sources including their own, at the tariff determined by the Appropriate Commission under Section 62 of the Act.
(iii) It is desirable that purchase of energy from renewable sources of energy takes place more or less in the same proportion in different States.
To achieve this objective in the current scenario of large availability of such resources only in certain parts of the country, an appropriate mechanism such as Renewable Energy Certificate (REC) would need to be promoted.
Through such a mechanism, the renewable energy based generation companies can sell the electricity to local distribution licensee at the rates for conventional power and can recover the balance cost by selling certificates to other distribution companies and obligated entities enabling the latter to meet their renewable power purchase obligations. The REC mechanism should also have a solar specific REC.
(iv) Appropriate Commission may also provide for a suitable regulatory framework for encouraging such other emerging renewable energy [2025] 1 S.C.R. 251Municipal Corporation of Delhi v. Gagan Narang & Ors. Etc technologies by prescribing separate technology based REC multiplier (i.e. granting higher or lower number of RECs to such emerging technologies for the same level of generation).
Similarly, considering the change in prices of renewable energy technologies with passage of time, the Appropriate Commission may prescribe vintage based REC multiplier (i.e.
granting higher or lower number of RECs for the same level of generation based on year of commissioning of plant).
(2) States shall endeavor to procure power from renewable energy sources through competitive bidding to keep the tariff low, except from the waste to energy plants. Procurement of power by Distribution Licensee from renewable energy sources from projects above the notified capacity, shall be done through competitive bidding process, from the date to be notified by the Central Government.
16. It can thus be seen that clause (1) of Rule 6.4 provides that the Appropriate Commission shall fix a minimum percentage of the total consumption of electricity in the area of a distribution licensee for purchase of energy from renewable energy sources, taking into account availability of such resources and its impact on retail tariffs. It further provides that the cost of purchase of renewable energy shall be taken into account while determining tariff by SERCs and that the long-term growth trajectory of Renewable Purchase Obligations (RPOs) will be prescribed by the Ministry of Power in consultation with Ministry of New and Renewable Energy (MNRE).
17. Certain exceptions have been made to the applicability of the said clause. One of the exceptions is that, the Distribution Licensee(s) shall compulsorily procure 100% of the power produced from all the Waste-to-Energy plants in the State, in the ratio of their procurement of power from all sources including their own, at the tariff determined by the Appropriate Commission under Section 62 of the Act.
18. It is further to be noted that the following provision has been made in SWM Rules 2016:
252 [2025] 1 S.C.R.Digital Supreme Court Reports “9. Duties of the Ministry of Power.- The Ministry of Power through appropriate mechanisms shall,-
(a) decide tariff or charges for the power generated from the waste to energy plants based on solid waste.