M/S C & C Constructions Ltd. v. Ircon International Ltd.
- Citation
- 2025 INSC 138; [2025] 1 S.C.R. 1413
- Court
- Supreme Court of India
- Bench
- 2 Judges: Justice Abhay S. Oka, Justice Ujjal Bhuyan
- Decided
- 31 Jan 2025
- Case number
- CIVIL APPEAL No. 6657/2023
- Sections
- 37, 34, 16(2), 16, 23, 28
Not a certified copy. Text extracted from the judgment PDF published by the Supreme Court of India. Verify against the certified copy before relying on it. Source: Supreme Court of India, via the Indian Supreme Court Judgments dataset by Dattam Labs (CC-BY-4.0). Retrieved 17 Nov 2026, 12:21 am. Original source ↗
Preview: first 50% of the document.
[2025] 1 S.C.R. 1413 : 2025 INSC 138 M/s C & C Constructions Ltd.
v.
IRCON International Ltd.
(Civil Appeal No. 6657 of 2023)
31 January 2025 [Abhay S. Oka* and Ujjal Bhuyan, JJ.] Issue for Consideration Matter pertains to the order passed by the Division Bench of the High Court, dismissing an appeal u/s.37 of the Arbitration and Conciliation Act, 1996, holding that the requirement of clause 49.5 was never waived by the respondent, that clause 49.5 was a valid clause, upheld the arbitral award.
Headnotes† Arbitration and Conciliation Act, 1996 – s.37 – Arbitration award – Scope of interference in an appeal u/s.37 – Dispute between the appellant and the respondent over construction of Road Over Bridges – Case of the appellant that delay in construction work for the reasons attributable to the respondent, resulted in additional financial burdens – Appellant sought extension of time, and the same was extended by the respondent – Appellant then sought damages on account of delay on part of the respondent, however, the claims rejected – Thereafter, undertakings by the appellant that it would not claim anything extra other than escalation for the work executed – Two years later, the appellant invoked arbitration clause on basis of the claims raised – Arbitral tribunal rejected the claims based on clause 49.5 of GCC which disentitles the appellant from raising any claim for damages or compensation for failure or delay caused by the respondent in fulfilling its obligations under the contract – Petition u/s.34 by the appellant – Dismissed by the Single Judge of the High Court holding that the clause 49.5 would bar the appellant’s claim – Appeal before the Division Bench u/s.37 also dismissed – Correctness:
* Author 1414 [2025] 1 S.C.R.Supreme Court Reports Held: Scope of interference in an appeal u/s.37, in examining an order, setting aside or refusing to set aside an award, is limited and restricted – On facts, the appellant acted upon clause 49.5 and sought an extension of time on three occasions – Solemn undertaking by the appellant not to make any claim other than escalation in respect of delays in the completion of work, however, claim made contrary to the undertakings – By the undertakings, the appellant agreed not to make a claim contrary to what is provided in clause 49.5, thus, by conduct, the appellant was estopped from challenging the validity of clause 49.5 – Furthermore, Clause 49.4 would apply when the delay is not due to the respondent – In the said matter, the delay was on the part of the respondent, hence, clause 49.5 would apply and not clause 49.4 – Also it cannot be inferred that clause 49.5 was waived by the respondent – Respondent stated that the claim for financial burden would have to be dealt with together with the proposal for an extension of time, and the said claim cannot be processed separately – Thus, on two occasions, on specific requests made by the appellant under clause 49 of the GCC, the extension of time was granted by the respondent – Except sub-clause 5 of clause 49, no other sub-clause which provides for grant of extension when the delay was attributable to the respondent – Thus, the order passed by the Division Bench upheld – General Conditions of Contract – Clause 49.5. [Paras 19, 23, 26-29] Case Law Cited Larsen Air Conditioning and Refrigeration Company v. Union of India and Ors. [2023] 11 SCR 86 : (2023) 15 SCC 472; Konkan Railway Corporation Limited v. Chenab Bridge Project Undertaking [2023] 11 SCR 215 : (2023) 9 SCC 85 – relied on.
Pam Developments Pvt. Ltd. v. State of West Bengal [2019] 9 SCR 252 : (2019) 8 SCC 112; ONGC v. Wig Brothers Builders and Engineers Private Limited (2010) 13 SCC 377 – referred to. List of Acts Arbitration and Conciliation Act, 1996.
List of Keywords Arbitration award; Arbitral award; Arbitration clause; Scope of interference in appeal u/s.37; Construction of Road Over Bridges; Delay in construction work; Additional financial burdens; Extension [2025] 1 S.C.R. 1415M/s C & C Constructions Ltd. v. IRCON International Ltd. of time; Damages; Escalation for the work executed; Claim for damages or compensation; Solemn undertaking; Estopped from challenging validity of clause 49.5; Delay; Financial burden; General Conditions of Contract Clause 49.5.
Case Arising From CIVIL APPELLATE JURISDICTION: Civil Appeal No. 6657 of 2023 From the Judgment and Order dated 01.03.2021 of the High Court of Delhi at New Delhi in FAO (OS) (COMM) No. 36 of 2021 Appearances for Parties Vikas Goel, Tarun Dua, Ritesh Sharma, Pragun Dua, Ms. Anisha Dahiya, Deepal Hooda, Rahul Shyam Bhandari, Advs. for the Appellant.
Gaurav Pachnanda, Sr. Adv., Sidhant Goel, Mohit Goel, Shubham S Saxena, Karmanya D Sharma, Ms. Nikita Jaitly, Ms. Avni Sharma, Sahil Tagotra, Advs. for the Respondent.
Judgment / Order of the Supreme Court Judgment Abhay S. Oka, J.
FACTUAL ASPECTS
1. This appeal arises out of the impugned judgment and order of the Division Bench of the High Court of Delhi dated 1 st March, 2021, which is passed in an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (for short, ‘the Arbitration Act’).
2. We refer to a few factual aspects of the case. An agreement dated 28 th June, 2012 was entered into between the appellant and the respondent for constructing five Road Over Bridges (for short, ‘ROBs’) and their approaches at different locations in the State of Rajasthan. The schedule of completion in respect of each ROB was different. The locations where ROBs were to be constructed have been described as LC-200, LC-89, LC-228, LC-233 and LC-108. According to the appellant’s case, the work at the sites was delayed for the reasons attributable to the respondent. According to the appellant’s case, 1416 [2025] 1 S.C.R.Supreme Court Reports the respondent withdrew the work relating to the construction of two ROBs (LC-200 and LC-233) from the scope of work and certified the completion of the remaining work. There is no dispute that we are not concerned with LC-200 and LC-233 in this appeal. In the case of LC-89 and LC-228, the scheduled completion date was 15 th September, 2013. For LC-108, it was 16 th July, 2013. As per the completion certificate dated 22 nd March 2016, the work of LC-89 was completed on 8 th October 2014, and the work of LC-228 was completed on 21 st March 2015. According to the appellant’s case, work at LC-108 was completed on 31 st March 2017.
3. On 19th June 2013, the appellant addressed a letter to the respondent’s General Manager stating that the construction delay of ROBs at LC- 108 was due to various hindrances at the site. By the said letter, the appellant requested the respondent to grant an extension of 264 days. The appellant contended that the delay in construction work has resulted in an additional financial burden on account of the establishment and overheads, etc., for a longer period than planned, for which the appellant would be claiming separately. By the reply dated 14 th October 2013, the respondent informed the appellant that the statement of the appellant that it would be claiming separately for financial burden was not acceptable. The respondent stated that the claim would have to be considered along with the prayer for extension. Therefore, the respondent requested the appellant to submit a detailed claim immediately so that the prayer for an extension of time could be considered. Separate letters dated 30 th August, 2013 were addressed by the appellant to the respondent regarding LC-89 and LC-228 for grant of extension by 430 and 437 days, respectively. By a letter dated 29 th November, 2013, the respondent granted an extension of time as follows:
LC No. Extension Upto Penalty 228 20th March, 2014 With Penalty 89 28th February, 2014 With Penalty 108 31st March, 2014 Without Penalty
4. On 28 th February, 2014, 09 th April, 2014 and 19 th April, 2014, the appellant again applied for a grant extension of time regarding LC Nos. 89, 228 and 108, respectively. By a letter dated 24th May, 2014, the respondent granted an extension of time as follows: [2025] 1 S.C.R. 1417M/s C & C Constructions Ltd. v. IRCON International Ltd. LC No. Extension Upto Penalty 228 31st January, 2015 Without Penalty 89 30th November, 2014 Without Penalty 108 15th December, 2014 Without Penalty
5. By letters dated 03 rd September, 2014, the appellant submitted separate claims concerning the three ROBs for damages on account of the delay on the part of the respondent. By letters dated 14th October, 2014, the respondent rejected the claims. The appellant applied for further extension of time by letters dated 08 th January, 2015. In response, the respondent addressed a letter dated 09th January, 2015 by which the appellant was called upon to give undertakings to the effect that the appellant will not claim anything extra other than escalation for the work executed. The appellant submitted undertakings on 14th January, 2015 accordingly.
6. The appellant invoked the arbitration clause on 25 th January 2017. The appellant filed a statement making a claim for Rs. 44.11 crores under 15 substantive heads besides the claim of interest and costs. The respondent filed its statement of defence on 25th August, 2017.
7. The respondent filed an application under Section 16(2) of the Arbitration Act. It was contended in the said application that clause 49.5 of the General Conditions of Contract (for short, ‘GCC’) disentitles the appellant from raising any claim for damages or compensation for failure or delay caused by the respondent in fulfilling its obligations under the contract. The Arbitral Tribunal passed the order in the respondent’s application under Section 16 of the Arbitration Act in nature of an award dated 21 st December, 2019 by which all claims were rejected based on clause 49.5 of GCC.
8. Aggrieved by the impugned award dated 21 st December 2019, the appellant preferred a petition under Section 34 of the Arbitration Act. The learned Single Judge of the High Court of Delhi dismissed the petition, holding that a term like clause 49.5 of the GCC would bar the appellant’s claim. Moreover, the appellant had accepted the communication dated 14th October 2014, issued by the respondent dismissing the claim. It was also held that clause 49.5 was valid and, after the appellant accepted the same, it could not contend to the contrary.
1418 [2025] 1 S.C.R.Supreme Court Reports
9. Being aggrieved by the judgment of the learned Single Judge, the appellant preferred an appeal before the Division Bench of the High Court of Delhi by invoking Section 37 of the Arbitration Act. While dismissing the appeal, the Division Bench held that the requirement of clause 49.5 was never waived by the respondent. The Division Bench held that clause 49.5 was a valid clause. After holding that the powers of the Court while dealing with an appeal under Section 37 of the Arbitration Act are limited by Section 34, the Division Bench dismissed the appeal.
SUBMISSIONS
10. The learned counsel appearing for the appellant has made detailed submissions. His first submission is that the award of the Arbitral Tribunal was contrary to public policy and suffered from patent illegality. The learned counsel also pointed out that the main issue was whether a clause prohibiting the payment of damages, like clause 49.5, could be enforced. He submitted that the Arbitral Tribunal and the learned Single Judge failed to appreciate the crucial aspects striking at the root of the award. The learned counsel pointed out various decisions of the Delhi High Court and this Court. After relying upon several decisions of this Court, he urged that the parties to the contract cannot contract against the Indian Contract Act, 1872 (for short, ‘the Contract Act’). He submitted that the finding recorded by the Arbitral Tribunal that clause 49.5 aims to protect the interests of PSUs and the Government is illegal. He relied upon the decision of this Court in the case of Pam Developments Pvt. Ltd. v. State of West Bengal 1 . The learned counsel submitted that the additional documents filed by the appellant ought to be considered. Therefore, the learned counsel appearing for the appellant submitted that the impugned judgments deserve to be set aside.
11. Learned counsel for the respondent submitted that clause 49.5 of GCC read with clause 12 of the Special Conditions of Contract (for short ‘SCC’) are limitation of liability clauses. These clauses are not in conflict with either Section 23 or Section 28 of the Contract Act. He submitted that if clause 49.5 of GCC and clause 12 of SCC are read together, it is apparent that in case of delay or fault on the
1 (2019) 8 SCC 112
[2025] 1 S.C.R. 1419M/s C & C Constructions Ltd. v. IRCON International Ltd. part of the employer (respondent), a reasonable extension of time can be granted and payment of price variation as per the formula agreed between the parties in the contract itself can be made. Learned counsel submitted that this Court has consistently upheld the enforceability of limitation of liability clauses. He relied upon what is held in paragraph 10 of the decision of this Court in the case of ONGC v. Wig Brothers Builders and Engineers Private Limited2 . He submitted that the appellant made an irreversible election to accept the extension of time in terms of the agreed scheme of the contract between the parties without payment of liquidated damages. Therefore, the appellant is not entitled to make any additional claim for compensation and/or damages beyond the stipulations in the contract and contrary to the express prohibition in clause 49.5 of GCC. He pointed out the letters addressed by the respondent by which initially liquidated damages/penalty were imposed on the appellant for the delay. However, on the request made by the appellant, the respondent granted an extension of time by waiving liquidated damages. Therefore, the appellant made an irreversible election to accept an extension of time under clause 49.5 of GCC. He relied upon three letters addressed by the appellant in which the appellant agreed not to make any claim other than escalation against the respondent because of the delay on the part of the respondent for which an extension of time has been sought. He pointed out that the claim for damages was raised two years after the date of the last extension. Learned counsel would, thus, submit that the appellant has lost its right to challenge clause 49.5 and therefore, no interference is called for with the impugned judgment.
OUR VIEW
12. We are concerned with three ROBs bearing numbers LC-89, LC-228 and LC-108. Clause 49.5 of GCC reads thus: