Kishore Chhabra v. The State of Haryana & Ors.
- Citation
- 2025 INSC 419; [2025] 4 S.C.R. 327
- Court
- Supreme Court of India
- Bench
- 3 Judges: Justice Bhushan Ramkrishna Gavai, Justice Prashant Kumar Mishra, Justice K.V. Viswanathan
- Decided
- 31 Mar 2025
- Case number
- CIVIL APPEAL No. 8968/2013
- Sections
- 4, 6, 5, 9, 48(1), 4(1)
Not a certified copy. Text extracted from the judgment PDF published by the Supreme Court of India. Verify against the certified copy before relying on it. Source: Supreme Court of India, via the Indian Supreme Court Judgments dataset by Dattam Labs (CC-BY-4.0). Retrieved 17 Nov 2026, 12:20 am. Original source ↗
Preview: first 50% of the document.
[2025] 4 S.C.R. 327 : 2025 INSC 419 Kishore Chhabra v.
The State of Haryana & Ors.
(Civil Appeal No. 8968 of 2013)
01 April 2025 [B.R. Gavai, Prashant Kumar Mishra* and K.V. Viswanathan, JJ.] Issue for Consideration Appellant sought release of his land from acquisition.
Headnotes† Land Acquisition Act, 1894 – Punjab Scheduled Roads & Controlled Areas Restrictions of Unregulated Development Act, 1963 – Appellant is the owner in possession of the land in question – The State issued notification u/s.4 of the 1894 Act for acquisition of the land – The LAC passed an award and mentioned that the possession of the land acquired was already taken and the same vests with the Government – Appellant filed various writ petitions challenging land acquisition proceedings, which were dismissed – His last writ petition was dismissed mainly on the ground that the possession is deemed to have been taken and continuing with physical possession would not confer any right whatsoever upon the appellant – Correctness:
Held: In the instant case, by the virtue of the provisions and notification any land falling in the area was required to obtain Change of Land Use (CLU) for development – The appellant’s land fell within this controlled area, yet the appellant did not obtain any CLU – The requirement for CLU being a statutory mandate, release of land, in the absence of CLU is not permissible – As far as appellant’s plea of discrimination is concerned, the appellant’s case stands on a different footing in comparison to others inasmuch as the appellant has not obtained a valid CLU – Thus, the appellant’s plea of discrimination is rejected – However, since the appellant claims to be in continuous physical possession of the land wherein a factory is in operation and the department * Author 328 [2025] 4 S.C.R.Digital Supreme Court Reports has not satisfactorily controverted this aspect of the matter, on the special facts of this case, in exercise of power u/Art.142, this Court deems it appropriate to direct that the compensation payable to the appellant should be calculated under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 as on the date of commencement of the said Act. [Paras 7,8,10,13] Case Law Cited Sube Singh v. State of Haryana (2001) 7 SCC 545; Hari Ram v. State of Haryana [2010] 2 SCR 756 : (2010) 3 SCC 621; Sham Lal v. State of Punjab (2013) 14 SCC 393; Haryana State Industrial Development Corporation v. Shakuntla [2009] 15 SCR 413 : (2010) 12 SCC 448; Raghbir Singh Sehrawat v. State of Haryana [2011] 14 SCR 1113 : (2012) 1 SCC 792; Patasi Devi v. State of Haryana [2012] 7 SCR 387: (2012) 9 SCC 503; Usha Stud & Agricultural Farms (P) Ltd. v. State of Haryana [2013] 5 SCR 645 : (2013) 4 SCC 210; Women's Education Trust v. State of Haryana (2013) 8 SCC 99; Siemens Engg. & Mfg. Co. of India Ltd. v. Union of India [1976] Supp. 1 SCR 489 : (1976) 2 SCC 981; State of Punjab v. Bandeep Singh [2015] 10 SCR 496 : (2016) 1 SCC 724 – referred to.
List of Acts Land Acquisition Act, 1894; Punjab Scheduled Roads & Controlled Areas Restrictions of Unregulated Development Act, 1963; Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.
List of Keywords Acquisition; Land; Release of land from acquisition; Possession of land; Physical possession of land; Change of Land Use; Change of Land Use being a statutory mandate; Discrimination; Article 142 of Constitution.
Case Arising From CIVIL APPELLATE JURISDICTION: Civil Appeal No. 8968 of 2013 From the Judgment and Order dated 15.09.2011 of the High Court of Punjab & Haryana at Chandigarh in CWP No. 17307 of 2011 [2025] 4 S.C.R. 329Kishore Chhabra v. The State of Haryana & Ors. Appearances for Parties Advs. for the Appellant:
Nidhesh Gupta, Sr. Adv., Ms. Jhanvi Dubey, Ms. Vriti Gujral, Ms. Pallavi Singh, Ms. Vinny Shangloo, Rishabh Relan, G. Balaji. Advs. for the Respondents:
K. M. Nataraj, A.S.G., B.K. Satija, A.A.G., Samar Vijay Singh, Ms. Sabarni Som, Fateh Singh, Aman Dev Sharma, Aashish Chopra, J.P. Sharma, Ajit Rajput, Dr. Sushil Balwada.
Judgment / Order of the Supreme Court Judgment Prashant Kumar Mishra, J.
1. Challenge in this appeal is to the order passed by the High Court of Punjab and Haryana whereby the writ petition of the appellant, calling in question the order dated 17.08.2010 passed by the respondent/State rejecting his representation for release of his land from acquisition, has been dismissed.
2. Briefly stated, the facts of the matter are that the appellant is the owner in possession of the land and constructed area measuring 386 sq. yards and 3078 sq. yards at Sultanpur, Sonipat, Haryana having purchased the same from the owner of M/s. Haryana Kamoplast Industries, Sonipat vide sale deed dated 04.08.1986.
2.1 On 09.11.1992, the State of Haryana issued notification under Section 4 of the Land Acquisition Act, 1894 1 for acquisition of land for the development and utilization of land for residential and commercial area along with sector road at Sonipat. Amongst other villages, the land situated in appellant’s village-Sultanpur was also the subject matter of acquisition. The total area being 329.70 acres as per Section 6 Notification issued on 06.11.1993, the appellant’s land was also included in the Notification so issued. The appellant claims to have submitted objections under Section 5-A of the Act. The Land Acquisition Collector passed an Award No. 10 on 05.11.1995 mentioning that the 1 “the Act’ 330 [2025] 4 S.C.R.Digital Supreme Court Reports possession of the land acquired had already been taken vide Rapat Rozanamcha No. 229 dated 05.11.1995 and the same vests with the Government.
2.2 The appellant’s 1 st writ petition challenging the land acquisition proceedings was dismissed by the High Court and his 2nd writ petition filed in the year 2008 was dismissed as withdrawn as his representation was pending. The present is the third writ petition filed by the appellant seeking release of the land as also seeking quashing of the order dated 17.08.2010 whereby his request for release of the land was rejected by the State Government.
2.3 The High Court dismissed the writ petition mainly on the ground that the possession is deemed to have been taken and continuing with physical possession would not confer any right whatsoever upon the appellant.
SUBMISSIONS BY THE APPELLANT
3. Mr. Nidhesh Gupta, learned senior counsel appearing on behalf of the appellant strenuously urged that in respect of the same Notification of the same village the State has released the land, and on the other hand, land of the appellant has not been released although the same is similarly situated, as such, the appellant has been singled out in a discriminatory manner. Learned senior counsel would refer to and rely upon various orders passed by the State Government directing release of the land both at the pre-award and post-award stage. It is further submitted that there is a running factory on the subject land since 1970 i.e. even before the issuance of Notification under Section 4 of the Act, therefore, his case for release of the land squarely falls within the parameters set forth in the State Government’s policy dated 26.10.2007. Learned senior counsel would also urge that the order dated 17.08.2010 rejecting appellant’s representation is unsustainable as the same has been passed without assigning any reason. Learned senior counsel has placed reliance on “Sube Singh vs. State of Haryana”,2 “Hari Ram Vs. State of Haryana”,3 “Sham Lal vs State
2 (2001) 7 SCC 545
3 (2010) 3 SCC 621
[2025] 4 S.C.R. 331Kishore Chhabra v. The State of Haryana & Ors. of Punjab”,4 “Haryana State Industrial Development Corporation vs. Shakuntla”,5 “Raghbir Singh Sehrawat vs. State of Haryana”,6 “Patasi Devi vs. State of Haryana”,7 “Usha Stud & Agricultural Farms (P) Ltd. vs. State of Haryana”,8 “Women’s Education Trust vs. State of Haryana”,9 “Siemens Engg. & Mfg. Co. of India Ltd. vs. Union of India10 & “State of Punjab vs. Bandeep Singh”.11
SUBMISSIONS BY STATE OF HARYANA