Not a certified copy. Text extracted from the judgment PDF published by the Supreme Court of India. Verify against the certified copy before relying on it. Source: Supreme Court of India, via the Indian Supreme Court Judgments dataset by Dattam Labs (CC-BY-4.0). Retrieved 17 Nov 2026, 12:21 am. Original source ↗
Preview: first 50% of the document.
[2025] 2 S.C.R. 1273 : 2025 INSC 255 State of Kerala & Ors.
v.
Moushmi Ann Jacob (Civil Appeal No(s). 3178-3179 of 2025)
20 February 2025 [Sanjay Karol* and Manmohan, JJ.] Issue for Consideration Whether under Notification dated 25.02.2021 issued under the Kerala Conservation of Paddy Land and Wetland Act, 2008, a land owner with more than 25 cents is liable to pay conversion fee for the entire land holding or would the conversion fee be calculable for the portion of land that is in excess of 25 cents. Headnotes† Kerala Conservation of Paddy Land and Wetland Act, 2008 – Notification dated 25.02.2021 exempted landowners holding up to 25 cents from paying conversion fee – Respondent, owner of 14.57 acres, directed to pay conversion fee on total extent of land – Writ Petition against interpretation of Notification in High Court – Single Judge held fee should be calculated only on extent of land exceeding 25 cents – Judgment upheld by Division Bench and subsequent review dismissed – Dismissal of review petition challenged – Appeal allowed – Exemption provision to be strictly construed – Notification creates two distinct categories – Exemption available only if holding does not exceed 25 cents – Conversion fee to be calculated on entire land if holding exceeds 25 cents – High Court erred in merging the two categories – Classification held reasonable and consistent with Article 14 of the Constitution – Respondent liable to pay conversion fee on entire extent of land: Held: Respondent, owner of 14.57 acres land, sought change of nature of land to secure education loan – Competent authority directed payment of Rs.1,74,840 as conversion fee, being 10% of fair value of entire land – In Writ Petition, Respondent challenged the fee amount contending that 25 cents was exempt under Notification dated 25.02.2021 under the Kerala Conservation of * Author 1274 [2025] 2 S.C.R.Supreme Court Reports Paddy Land and Wetland Act, 2008 – Fee ought to be calculated only on land exceeding 25 cents — Single Judge held fee should be calculated only on extent exceeding 25 cents and not entire 14.57 acres – Same upheld by Division Bench and subsequent review dismissed by impugned order – Appeal allowed. Notification issued in furtherance of an Act is delegated legislation – Such subordinate legislation lacks the same level of immunity as plenary law and must yield to it – Instant dispute concerns a Notification granting exemption from payment of fees – Person claiming exemption must establish entitlement – Such Notification must be interpreted strictly and in accordance with the literal rule of interpretation – Plain reading of Notification shows that it creates two distinct categories: those with land up to 25 cents and those with land in excess of 25 cents – Object of exempting people belonging to the former class from payment of fee is to enable them to have ease in constructing without being burdened with conversion fee of the land – Nothing to show State did not have necessary competence to create two classes – High Court erred in fusing two distinct categories – Competent authority specified different fee categories proportionate to land, signifying intent to form distinct classes – State is permitted reasonable classification, provided it bears a reasonable nexus to the object sought to be achieved – Principles of Article 14 to guide all State actions, including administrative, such as the issuance of Rules or Notifications. [Paras 2-3, 13-20] Reliance also placed on Rule 12 Clause 9 of Kerala Conservation of Paddy Land and Wetland Rules, 2008, which states no fee is payable up to 25 cents, and 10% of the fair value is payable for land above 25 cents up to 1 acre – Respondent liable to pay conversion fee on total extent of land in ownership. [Paras 23-25] Case Law Cited Registrar of Cooperative Societies, Trivandrum v. K. Kunjabmu, 1979 INSC 249 : [1980] 2 SCR 260 : (1980) 1 SCC 340; C.C.E. v. Hari Chand Shri Gopal, 2010 INSC 785 : [2010] 13 SCR 820 : (2011) 1 SCC 236; Commissioner of Customs (Import), Mumbai v. Dilip Kumar & Co., 2018 INSC 646 : [2018] 7 SCR 1191 : (2018) 9 SCC 1; Balram Kumawat v. Union of Indian & Ors., 2003 INSC 426 : [2003] Supp. 3 SCR 24 : (2003) 7 SCC 628; Natural Resources Allocation, In Re: Special Reference No. 1 of 2012, 2012 INSC 428 : [2012] 9 SCR 311 : (2012) 10 SCC 1 – relied on. [2025] 2 S.C.R. 1275State of Kerala & Ors. v. Moushmi Ann Jacob Indian Express Newspapers (Bombay) Pvt. Ltd. v. Union of India, 1984 INSC 231 : [1985] 2 SCR 287 : (1985) 1 SCC 641; Swami Vivekanand College of Education & Ors. v. Union of India & Ors., 2011 INSC 752 : [2011] 12 SCR 941 : (2012) 1 SCC 642; Charanjit Lal Chowdhury v. Union of India, 1950 INSC 36 : [1950] 1 SCR 869 : (1950) SCC 833; Kewal Singh v. Lajwanti, 1979 INSC 197 : [1980] 1 SCR 854 : (1980) 1 SCC 290; Harbans Lal v. State of H.P, 1989 INSC 224 : [1989] 3 SCR 662 : [1989] 4 SCC 459; Chhattisgarh Rural Agriculture Extension Officers Assn. v. State of M.P, 2004 INSC 229 : [2004] 3 SCR 821 : (2004) 4 SCC 646; Khalsa University v. State of Punjab, 2024 INSC 751 : [2024] 10 SCR 445 : 2024 SCC OnLine SC 2697 – referred to.
List of Acts Constitution of India; Kerala Conservation of Paddy Land and Wetland Act, 2008; Kerala Conservation of Paddy Land and Wetland Rules, 2008.
List of Keywords Land reclassification; Conversion fee; Delegated legislation; Subordinate legislation; Exemption notification; Exemption clause; Interpretation; Strict construction; Literal rule; Reasonable classification; Article 14.
Case Arising From CIVIL APPELLATE JURISDICTION: Civil Appeal No(s). 3178-3179 of 2025 From the Judgment and Order dated 01.08.2023 and 04.10.2023 of the High court of Kerala at Ernakulam in WA No. 983 of 2023 and RP No. 894 of 2023 respectively With Civil Appeal No(s). 3180-3181 and 3220-3221 of 2025 Appearances for Parties Advs. for the Appellants:
Shaji P. Chaly, Sr. Adv., Nishe Rajen Shonker, Mrs. Anu K Joy, Alim Anvar.
1276 [2025] 2 S.C.R.Supreme Court Reports Advs. for the Respondent:
Raghenth Basant, V Chitambaresh, Sr. Advs., Manish Tiwari, Vishnu Pazhanganat, Ms. Kaushik Akira Sharma, Ms. Hima Bhardwaj, Jogy Scaria, Mrs. Beena Victor, C Govind Venugopal, Ms. M Priya, Ashwani Kumar Soni, M Gireesh Kumar, Ankur S. Kulkarni, A S Naushad, Ms. Puspita Basak, Tarun.
Judgment / Order of the Supreme Court Judgment Sanjay Karol, J.
Leave Granted.
2. The issue in these appeals is the construction of a Government Notification exempting the payment of fee upon reclamation of land originally reflected in the records of the State as ‘paddy land’ in accordance with the Kerala Conservation of Paddy Land and Wetland Act, 2008 1 . The Learned Single Judge vide judgment and order dated 6 th February 2023 2 passed in WP(C)No.23400/2022 held that the fee payable by a person would be calculable for the portion of land that is in excess of 25 cents, since that much stands exempted. Such a finding in law was confirmed by the learned Division Bench vide judgment and order dated 1 st August 2023 in WA No.983/2023, and a review filed thereagainst in R.P. No.894/2023 was dismissed by order dated 4 th October 2023. The appellant-State takes exception to such a reading of the Notification, and hence, it is before us.
3. The background in which the writ petitions, their findings and subsequent review petition impugned herein, arose, is: - 3.1 The Respondent is the owner of land measuring 14.57 acres having Survey Number 97/2 of Karikode Village in Thodupuzha Taluk. On 26 th October 2019, with the intention of putting the land to alternate use, i.e., using it to secure an education loan, made an application to the competent authority under Form 6 of Section 27 of the Act. Thereafter an application was further 1 “The Act”
2 In W.P (C) 23400 of 2022 [2025] 2 S.C.R. 1277State of Kerala & Ors. v. Moushmi Ann Jacob made to remove the said land from the ‘data bank’, under Form 5 of the Act.
3.2 The Revenue Officer, Idduki, by way of Notice dated 27th January 2021, informed the respondent that the property is de-notified as per the Act, thereby, she was also directed to deposit a sum of Rs. 1,74,840/-, which is 10% of the value of the property, which totals to Rs.17,40,000/-. The relevant extract thereof, is as below: - “As per reference no.1 you had submitted application for the change of nature of 14.57 Are property situated at survey no. 97/2, Thodupuzha Taluk, Karikod Village, Block 33. The property mentioned as field in the revenue records. As per reference no.2 the Kerala paddy and wetland (amendment act 2018) section 12(9) the nature of the unnotified land can be change by the panchayat on payment of 10% of the property value for properties having the measurement of 20.23 Are. As per reference no.5 report, it is understood that the applicant’s property comes with the panchayat limit. As per reference no.6 The Kerala Paddy and wetland (amendment act 2018) Rule (4E) (4F) the property has been removed from the data bank of the Kerala paddy. Hence, the applicant’s property is not in the data bank therefore as per the Kerala paddy and wetland (amendment act 2018) the property is unnotified.
It is understood from the application that the nature of the property needs to be changed for the purpose of taking education loan. As per the Kerala paddy and wetland (amendment act 2018) rule 12(9) if the nature of property which needs to be changed is above 3000 square feet, for every square feet, a fees of Rs.100/- need to be remitted. If there no plan of constructing any building in the applicant’s property, then there is no need of remitting any fees.
Under the Kerala paddy and wetland (amendment act 2018) section 27A for change of nature of the unnotified land, the value of the property will be 1278 [2025] 2 S.C.R.Supreme Court Reports considered as; the value of the property situated near to the applicant’s property, and if there is no value is fixed for the nearby properties, then the value will be fix according to the nature of the property. Hence as per reference no.3 circular the property comprising survey no.95/1 is the nearby property to the applicant’s property and as per the registered the value of that property is mentioned as 60,000/- for 1 Are. Hence the fees for the present application can be considered according to the value of the nearby property. As per reference no.7 the Karikod village officer has valued the property accordingly. Hence the amount needs to be paid for the change of nature of the property is mentioned hereunder.
1 Value for 1 are as per 2010 notification Rs.60,000/- 2 100% increase as per 2020 notification Rs.60,000/- 3 Current value of the property Rs.1,20,000/- 4 The area of the property 14.57 Are 5 Total value of the property 120000 x 14.57 Rs.17,48,400/- 6 The total amount to be paid Rs.1,74,840/- As per the recent Government notification, the nearby property in survey no.95/1 has a value of Rs.1,20,000/- per 1 Are. Therefore, the value of 14.57 area property will be 17,48,400/-. The property comes under the panchayat limit, therefore for change of nature of the property 10% of the total value i.e., Rs.1,74,840/- must paid as per the Kerala paddy and wetland (amendment ac 2018) rule 12(9). The payment receipt need be produced before this office. It is informed that if there is any change in the fees calculated or any miscalculation happens while considering the value of the property, then the balance amount if any has to be paid by the applicant.”
[2025] 2 S.C.R. 1279State of Kerala & Ors. v. Moushmi Ann Jacob 3.3 The appellant-State issued a Notification on 25th February 2021 granting exemption from paying reclamation fee in respect of lands up to 25 cents, stating that lands in excess of the prescribed limit shall be charged such fee at 10% of the fair value. Since it is this Notification, and its interpretation as undertaken by the Courts below, which is the primary bone of contention, it shall be useful to reproduce the same, in toto, as under:- “ANNEXURE-P/2 //ENGLISH TRANSLATION//
EXHIBIT-P5
Emblem
GOVERNMENT OF KERALA
Abstract Revenue Department – Issuance of revised rate of Conversion Charges for change of nature of lands which are not notified under Section 27(A) of the Kerala Conservation of Paddy & Wet Land Act & Rules, 2008 – orders issued – reg _______________________________________ Revenue (P) Department G.O. (Rt) No.1166/2021/Rev Thiruvananthapuram, Dated 25.02.2021 Ref : Interim order of the Hon’ble High Court of Kerala Dated 08.01.2021 in WP©14312/2019 & Connected cases.
ORDER
Directions are hereby issued in consonance with the observations made by the Hon’ble High Court of Kerala. In the matter referred above and based on the needs of the public in general, the Conversion fees for change of nature of land, those lands, which are not notified under Section 27(A) of the Kerala Conservation of Paddy & Wet Land Act & Rules, 2008, the following rate of Conversion Charges are imposed and unifying the rate for change of nature of land in Panchayath, Municipality and Corporation, 1280 [2025] 2 S.C.R.Supreme Court Reports 1) Lands, which are having an extent up to 25 Cents can be considered for category change without any fee. Only to those lands not exceeding an extent of 25 cents as on 30 th December 2017 can avail the above benefit.
2) Properties which were lying as a single unit up to 30.12.2017 and was divided into several plots having 25 cents or below that will not get the above benefit. In such cases, the entire land has to be considered as a single unit and calculate the fee.
3) Those properties having more than 25 cents in extent, shall impose the fee at the rate of 10% of the fair value, irrespective of the fact, whether it is situated in Municipality, Corporation or Panchayath.
4) Those properties having more than One Acre in extent, the rate of fee to be imposed is 20% of the fair value irrespective of the fact whether it is situated in Municipality, Corporation or Panchayath.
5) Rate of fee with respect to the construction carried out in the land wherein category change is carried out, will remain as the current rate.
The above amendments shall come into force from this day itself.
By order of the Governor Dr. A. Jayathilak IAS Principal Secretary”
(Emphasis supplied)
3.4 Subsequently, a clarification was also issued on 23rd July 2021, inter alia, making the following points –
(a) The fee waiver shall be applicable to only those applications received after the date of the Notification, submitted in place thereof;
(b) A few exemptions shall be allowed in terms of the Notification, for those properties which do not exceed [2025] 2 S.C.R. 1281State of Kerala & Ors. v. Moushmi Ann Jacob the exempted amount of land, i.e., 25 cents as on 30th December 2017;
(c) Applications in the name of one person as on 30 th December 2017 which may either be under the same or different survey numbers, in the same location as one entity or in separate locations, can be considered under single or separate applications. However, if the total amount of land is in excess of 25 cents, then the benefit of the exemption cannot be allowed. The applicant is also required to submit an affidavit to the effect that the land in respect of which the entry is to be altered, measures less than 25 cents.
PROCEEDINGS IN THE WRIT PETITION
4. The respondent, aggrieved by the ask of the competent authority to pay the amount of Rs.1,74,840/-, approached the High Court under Article 226 of the Constitution of India.
5. The case of the respondent before the High Court, as can be understood from record, was :
5.1 The respondent submitted an application for permission under Section 27A of the Act on 26th October 2019, before the year 2020. The application was not rejected, nor was a fresh application submitted, so the relevant date for consideration should be the submission date, as per the Court’s ruling. The appellants wrongly determined that the respondent could only submit an application after the removal of the land’s entry from the data bank in 2020. The High Court has apparently, clarified, that the removal of an erroneous entry from the data bank is merely a technicality and does not affect the right to submit the application, which depends on meeting the requirements of Section 27A, not on the data bank’s correction.
5.2 The respondent was also entitled to an exemption of up to 25 cents of land under the Circular reproduced supra, but the appellants incorrectly calculated the fees for the entire 14.57 Acres, which is illegal. The Court further emphasized that once an error in the data bank is corrected, the matter is treated as if it was corrected on the original date the data bank was prepared, i.e., 12 th August 2008. Therefore, the date 1282 [2025] 2 S.C.R.Supreme Court Reports of application (26 th October 2019) should be the relevant date for determining the fees.
5.3 It was submitted that the appellants’ reliance on the fair value of adjacent land to calculate the fees, ought to be rejected as the property in question had a fixed fair value of Rs.57,000/- and the fair value applicable should be that of the subject property, as per the ruling in Ajithkumar Shenoy v. Revenue Divisional Officer3 and the related case law. Since the application was submitted before 20th February, 2021, the appellants’ must follow the High Court’s decisions and treat the application date as 26th October 2019, making their interpretation of the law incorrect.
6. In response, by way of a counter-affidavit, the 3 rd appellant herein, the Revenue Divisional Officer 4 , submitted as under : 6.1 The orders under challenge before the High Court suffered with no illegality.
6.2 An application under Form-6 is maintainable only in respect of ‘unnotified land’. The land of the respondent herein is reflected in the data bank as ‘paddy land’ which was only de-notified vide order dated 13 th January 2021. There is no illegality therefore in taking the fair value as on the said date. The respondents’ application under Form-6 dated 26 th January 2019 can only be termed as a premature application, defective in nature. 6.3 The judgment relied on, i.e., Writ Petition (Civil) No.12721 of 2020 is not applicable to the given case. The contention of the respondent is that the date of the application, i.e., 26 th October 2019 is to be considered for the determination of fair value, is misconceived and ought to be rejected.
6.4 The further contention that the respondents’ liability to pay fee is to the extent that remains of the 14.5 Acres after having removed the 25 cents that are exempted from the payment of fee, is also misconceived.
7. Two primary questions arose for consideration by the learned Single Judge – one, concerning the maintainability of an application under 3 W.P.(C)No.12721/2020 4 For short ‘RDO’ [2025] 2 S.C.R. 1283State of Kerala & Ors. v. Moushmi Ann Jacob Form-6; and two, whether the fee payable shall be calculable after having deducted the 25 cents as exempted by the Notification. The learned Single Judge in judgment dated 6 th February 2023 having referred to Section 27A, observed that an application under Form-6 becomes maintainable after an order has been passed by the RDO. That being the case, the respondents’ application could have only been filed after 13 th January 2021, when the application under Form-5, for correction of a mistake in the data bank and deemed removal of property therefrom was allowed. On the next issue, it was held that the 10% of fair value should be calculable on the portion of the total land, exceeding the 25 cents exempted by the Notification.
8. As the demand notice was set aside, the RDO was directed to make a fresh calculation of the payment of fee, as it stood immediately after January, 2021 to the extent of 4.45 Acres of land.
PROCEEDING IN WRIT APPEAL
9. The State of Kerala filed Writ Appeal No.983 of 2023 which was dismissed vide judgment dated 1 st August 2023 holding that there is no reason to interfere with the judgment of the learned Single Judge as the same has been passed in terms of the statutory provisions and schedule of fee.
10. Review Petition No.894 of 2023 questioning the said findings of the Division Bench was also dismissed vide order dated 4 th October, 2023 observing that :
“5. A reading of the above notification leaves no room for doubt that the fee for conversion of land is payable only for lands in excess of 25 cents. Being so, the contention that, if the land exceeds 25 cents, conversion fees will have to be paid for the entire extent, including the 25 cents, can only be rejected. The learned Single Judge having taken the same view and the writ appeal having been dismissed finding the view taken to be correct, we find no reason to come to a different conclusion by exercising the power to review.”
CASE BEFORE THIS COURT
11. By way of the special leave petition, the following grounds have been urged in challenging the judgment of the learned Division Bench : 1284 [2025] 2 S.C.R.Supreme Court Reports