M/S Ajay Protech Pvt. Ltd. v. General Manager & Anr.
- Citation
- 2024 INSC 889; [2024] 11 S.C.R. 850
- Court
- Supreme Court of India
- Bench
- 2 Judges: Justice Pamidighantam Sri Narasimha, Justice Sandeep Mehta
- Decided
- 22 Nov 2024
- Case number
- CIVIL APPEAL No. 13004/2024
- Sections
- 29A(4), 29A(5), 29A, 11, 29A(1), 29A(3), 12, 138, 23
Not a certified copy. Text extracted from the judgment PDF published by the Supreme Court of India. Verify against the certified copy before relying on it. Source: Supreme Court of India, via the Indian Supreme Court Judgments dataset by Dattam Labs (CC-BY-4.0). Retrieved 17 Nov 2026, 12:24 am. Original source ↗
Preview: first 50% of the document.
[2024] 11 S.C.R. 850 : 2024 INSC 889 M/s Ajay Protech Pvt. Ltd.
v.
General Manager & Anr.
(Civil Appeal No. 13004 of 2024)
22 November 2024 [Pamidighantam Sri Narasimha* and Sandeep Mehta, JJ.] Issue for Consideration Issue arose as to whether the application for extension can be entertained if it is filed after the expiry of the Arbitral Tribunal’s mandate; and whether the application filed u/s.29A(4) of the Arbitration and Conciliation Act, 1996 for extension of the mandate of the arbitral tribunal ought to have been allowed by the High Court. Headnotes† Arbitration and Conciliation Act, 1996 – s.29A(4) – Time limit for arbitral award – Extension of time – Application u/s.29A(4), for extension of the mandate of the arbitral tribunal – High Court, if ought to have allowed the same:
Held: Wording of s.29A(4) clearly and explicitly enables a court to extend the Tribunal’s mandate after expiry of the statutory and extendable period of 18 months – Application for extension can be filed either before or after the termination of the Tribunal’s mandate upon expiry of the statutory and extendable period – As per s.29A(5), the decision to extend the time is an exercise of discretion by the court and must be done on sufficient cause being shown, and on such terms and conditions that the court deems fit – Arbitration and Conciliation Act adopts the well-known language of limitation statutes and provides that the Court can extend the time if it finds that there is sufficient cause – Primary objective in rendering an arbitral award is to resolve disputes through the agreed dispute resolution mechanism as contracted by the parties – Thus, 'sufficient cause' should be interpreted in the context of facilitating effective dispute resolution – On facts, the pandemic had commenced even before the expiry of 12 months from the completion of pleadings, this Court excluding the period between 15.03.2020 to 28.02.2023 in Re: Cognizance for Extension of Limitation’s * Author [2024] 11 S.C.R. 851M/s Ajay Protech Pvt. Ltd. v. General Manager & Anr. case, and the agreement between the parties on 05.05.2023 to seek extension of time by filing an application before the Court, there is sufficient cause for extension of the period for making of the award – Reasoning adopted by the High Court in holding that there is a delay of 2 years, 4 months in filing the application is erroneous – Order and judgment passed by the High Court set aside – Period for making of the award by the Arbitral Tribunal is extended. [Paras 2, 8, 10, 11, 12-18] Case Law Cited In re: Cognizance for Extension of Limitation [2021] 2 SCR 640 : (2022) 3 SCC 117; Rohan Builders (India) Pvt. Ltd. v. Berger Paints India Ltd. [2024] 9 SCR 473 : 2024 SCC OnLine SC 2494 – relied on.
List of Acts Arbitration and Conciliation Act, 1996.
List of Keywords Application for extension of mandate of arbitral tribunal; Time limit for arbitral award; Arbitral award; Sufficient cause; COVID pandemic; Period of limitation; Delay; Efficiency in the conduct of arbitral proceedings; Dispute resolution remedy through arbitration; Re: Cognizance for Extension of Limitation case.
Case Arising From CIVIL APPELLATE JURISDICTION : Civil Appeal No. 13004 of 2024 From the Judgment and Order dated 03.11.2023 of the High Court of Gujarat at Ahmedabad in MCA No. 1 of 2023 Appearances for Parties Gaurav Agrawal, Sr. Adv., C. George Thomas, Manan Daga, Ms. Kaarunya Lakshmi, Ansh Mittal, Advs. for the Appellant. Vikramjit Banerjee, A.S.G., Ms. Nisha Bagchi, Sr. Adv., Amrish Kumar, Siddharth Sinha, Shubendu Anand, Navanjay Mahapatra, Ms. Sansriti Pathak, Bhuvan Kapoor, Ashok Panigrahi, Sandeep Singh, Advs. for the Respondents.
852 [2024] 11 S.C.R.Digital Supreme Court Reports Judgment / Order of the Supreme Court Judgment Pamidighantam Sri Narasimha, J.
1. Leave granted.
2. The short issue in this appeal is whether the application filed by the appellant under Section 29A(4) of the Arbitration and Conciliation Act, 1996 1 for extension of the mandate of the Arbitral Tribunal ought to have been allowed by the High Court. The text of Section 29A was sufficient for us to come to the conclusion that the Court has the power and jurisdiction to extend the period. Further, in the facts and circumstances of the case, we found that there is ‘sufficient cause’ for the Court to extend the period for making the Award. Thus, we have allowed the appeal and extended the time till 31 st December, 2024 to make the Award. In this context, we have also explained the purport of the expression sufficient cause employed in this section.
3. The brief facts are as follows. The appellant entered into a works contract with respondent no. 1. Subsequently when disputes arose, appellant sought resolution through arbitration by issuing a notice on 12.02.2018. Appellant’s application under Section 11 of the Act for appointment of a sole arbitrator was allowed by the High Court by orders dated 08.02.2019 and 15.02.2019.
3.1 After the first meeting of the Arbitral Tribunal on 24.06.2019, parties were given time to complete their pleadings, which were in-fact completed on 09.10.2019. The statutorily stipulated 12-month period under Section 29A(1) for making the award commences from this date, and would expire on 08.10.2020. Further, as the parties can extend this period by another 6 months by mutual consent as per Section 29A(3), upon such mutual extension the time for making the award got extended till 09.04.2021. Therefore, the 18-month period, which commenced from 09.10.2019, would have naturally expired on 09.04.2021. 3.2 However, before the expiry of the said period, in fact even before the first stretch of 12 months, the nation was affected by 1 Hereinafter “the Act”.
[2024] 11 S.C.R. 853M/s Ajay Protech Pvt. Ltd. v. General Manager & Anr. the COVID pandemic. Taking note of this situation, this Court in Re: Cognizance for Extension of Limitation by order dated 10.01.2022 passed orders declaring that the period between 15.03.2020 and 28.02.2022 shall be excluded in computing periods of limitation under Sections 23(4) and 29(A) of the Act. 2 The relevant portion of the said order is as under:
“5. Taking into consideration the arguments advanced by the learned counsel and the impact of the surge of the virus on public health and adversities faced by litigants in the prevailing conditions, we deem it appropriate to dispose of MA No. 21 of 2022 with the following directions:
***
5.4. It is further clarified that the period from 15-3-2020 till 28-2-2022 shall also stand excluded in computing the periods prescribed under Sections 23(4) and 29-A of the Arbitration and Conciliation Act, 1996, Section 12-A of the Commercial Courts Act, 2015 and provisos (b) and (c) of Section 138 of the Negotiable Instruments Act, 1881 and any other laws, which prescribe period(s) of limitation for instituting proceedings, outer limits (within which the court or tribunal can condone delay) and termination of proceedings.”
3.3 Returning to the arbitral proceedings, the Arbitral Tribunal framed issues on 21.11.2019 and posted the matter for arguments for December 2019 and January 2020 but was compelled to adjourn the proceedings due to the pandemic. The record reveals that the proceedings resumed in the year 2022, and in fact, the hearing was concluded on 05.05.2023. It is an admitted fact that the parties to the arbitration agreement have submitted before the Arbitral Tribunal that they would move the Court under Section 29A(4) of the Act for appropriate orders for extension of time for making the award. In furtherance of the undertaking, an application under Section 29A(4) was filed by the appellant before the Gujarat High Court on 01.08.2023.
2 In re: Cognizance for Extension of Limitation (2022) 3 SCC 117. 854 [2024] 11 S.C.R.Digital Supreme Court Reports
4. By the order dated 03.11.2023 impugned before us, the High Court dismissed the application. The High Court reasoned that the initial statutory period of 12 months expired on 08.10.2020, and the same was extended by the mutual consent of the parties till 09.04.2021. Noting that the application for extension was preferred only in August 2023, High Court held that there is no explanation for a delay of more than 2 years, 4 months in approaching it. The High Court held that the mandate of the Arbitral Tribunal stood terminated on 09.04.2021, at which point there was not even an application for extension of time pending before it. In this view of the matter, the application was found to be misconceived, and was dismissed by the order impugned before us.
5. We have heard Mr. Gaurav Agrawal, learned senior counsel for the appellant, and Mr. Vikramjit Banerjee, learned ASG for the respondents.
5.1 Relying on this Court’s declaration Re: Cognizance for Extension of Limitation dated 10.01.2022 extending limitation on account of the pandemic, 3 Mr. Agrawal submits that the High Court ought to have excluded the period between 15.03.2020 and 28.02.2022 while determining the date on which the Tribunal’s mandate stood terminated. Further, he submits that the respondent had agreed to apply for extension of time before the Arbitral Tribunal, as is recorded in the Minutes of Arbitral Meeting dated 05.05.2023.
5.2 Mr. Vikramjit Banerjee, ASG, submits that even if the benefit of this Court’s order is considered, the Tribunal’s mandate expired on 31.10.2022, and there is still a nine-month delay in filing the application. Further, placing reliance on a recent decision of this Court in Rohan Builders (India) Pvt. Ltd. v. Berger Paints India Ltd., 4 he submits that an application under Section 29A(4) must be filed before the mandate of the Tribunal expires. It cannot be subsequently filed as the provision stipulates termination of the Tribunal’s mandate on expiry of the statutory and extendable period.
3 ibid.
4 2024 SCC OnLine SC 2494.
[2024] 11 S.C.R. 855M/s Ajay Protech Pvt. Ltd. v. General Manager & Anr.
6. Having heard learned senior counsel and the learned ASG, there are two issues that we must consider:
i. Whether the application for extension can be entertained if it is filed after the expiry of the Arbitral Tribunal’s mandate? ii. If yes, do the facts and circumstances warrant an extension in the present case?
7. When must an application under Section 29A(4) be filed. The first issue is no longer res integra in view of a recent decision of this Court in Rohan Builders (supra). Despite Mr. Banerjee’s reliance on this decision, we find that it squarely covers the issue against him. Before dealing with this decision, it is necessary to take note of the text and wording of the relevant portion of Section 29A of the Act: “29A. Time limit for arbitral award.— (1) The award in matters other than international commercial arbitration shall be made by the arbitral tribunal within a period of twelve months from the date of completion of pleadings under sub-section (4) of section 23: