The Chief Manager, Central Bank of India & Ors. v. M/S Ad Bureau Advertising Pvt. Ltd & Anr.
- Citation
- 2025 INSC 288; [2025] 2 S.C.R. 1445
- Court
- Supreme Court of India
- Bench
- 2 Judges: Justice Sudhanshu Dhulia, Justice Prashant Kumar Mishra
- Decided
- 28 Feb 2025
- Case number
- CIVIL APPEAL No. 7438/2023
- Sections
- 2, 23, 19
Not a certified copy. Text extracted from the judgment PDF published by the Supreme Court of India. Verify against the certified copy before relying on it. Source: Supreme Court of India, via the Indian Supreme Court Judgments dataset by Dattam Labs (CC-BY-4.0). Retrieved 17 Nov 2026, 12:21 am. Original source ↗
Preview: first 50% of the document.
[2025] 2 S.C.R. 1445 : 2025 INSC 288 The Chief Manager, Central Bank of India & Ors.
v.
M/s Ad Bureau Advertising Pvt. Ltd & Anr.
(Civil Appeal No. 7438 of 2023)
28 February 2025 [Sudhanshu Dhulia* and Prashant Kumar Mishra, JJ.] Issue for Consideration Issue arose as to whether the borrower of a project loan, falls within the definition of ‘Consumer’ under the provisions of the Consumer Protection Act, 1986.
Headnotes† Consumer Protection Act, 1986 – s.2 (1)(d)(ii) – Definition of ‘Consumer’ – Borrower of project loan, if falls within the definition of ‘Consumer’ – Maintainability of the consumer complaint – Respondent-advertising and branding company defaulted on a project loan availed from the appellant-Bank for engaging in the post production of a movie – Initiation of proceedings, One Time Settlement between the parties and thereafter, issuance of No-Dues Certificate to the respondent and full-satisfaction memo filed before the DRT – However, the Bank incorrectly reported the name of the respondent to Reserve Bank of India as a defaulter with outstanding loan amount which caused loss of goodwill and reputation, and resulted in the respondent losing an exclusive advertising tender/license – Consumer complaint by the respondent alleging negligence and deficiency in service on part of the appellant – National Commission partly allowed the complaint and directed the Bank to pay compensation to the respondent – Sustainability: Held: Respondent is not a ‘consumer’ under the Act – Plea that post-production of a movie was a self-branding exercise, the sole purpose being building a brand name for the respondent in order to earn livelihood, thus no nexus to generation of profits, not convincing since the dominant purpose behind brand building itself was to attract more customers and consequently generate profits or increase revenue for the business – Fundamental nature of the transaction, availing of credit facility from Bank which was * Author 1446 [2025] 2 S.C.R.Supreme Court Reports purely business-to-business transaction entered into for commercial purpose, not altered – Transaction of obtaining a project loan had a close nexus with a profit-generating activity and the dominant purpose for getting the loan sanctioned was to generate profits upon successful post-production of the movie – Order passed by the National Commission set aside. [Paras 16, 18, 21] Case Law Cited National Insurance Company Limited v. Harsolia Motors & Ors. [2023] 3 SCR 448 : (2023) 8 SCC 362; Lilavati Kirtilal Mehta Medical Trust v. Unique Shanti Developers [2019] 14 SCR 563 : (2020) 2 SCC 265; Shrikant G. Mantri v. Punjab National Bank [2022] 5 SCR 945 : (2022) 5 SCC 42 – referred to.
List of Acts Consumer Protection Act, 1986; Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002; Recovery of Debts Due to Banks and Financial Institutions Act, 1993. List of Keywords Consumer; Deficiency in service; Project loan; Borrower of project loan; Consumer complaint; Postproduction of movie; Non-performing asset; One-time settlement; Delayed period interest; No-Dues Certificate; Full-satisfaction memo; Wilful defaulters; Doubtful and loss accounts; Airports Authority of India advertising tender/license; Wrongful reporting; Unfair trade practice; Serious breach of duty by bank; Business-to-business transaction; Business-to-consumer transaction; Dominant intention; Commercial purpose; Self-branding exercise; Loan for self-use; Direct nexus with profit generating activity; Maintainability of consumer complaint; Master Circular on Wilful Defaulters DBOD No. BC/CIS/47/20.16.002/94 dated 23.04.1994. Case Arising From CIVIL APPELLATE JURISDICTION: Civil Appeal No. 7438 of 2023 From the Judgment and Order dated 30.08.2023 of the National Consumers Disputes Redressal Commission, New Delhi in CC No. 23 of 2021 With Civil Appeal No. 3456 of 2025 [2025] 2 S.C.R. 1447The Chief Manager, Central Bank of India & Ors. v. M/s Ad Bureau Advertising Pvt. Ltd & Anr.
Appearances for Parties Advs. for the Appellants:
Viresh B. Saharya, Akshat Agarwal, Rishabh Mathur, Ashish Wad, Manoj Wad, Ms. Swati Arya, Ms. Akriti Arya, Mohd. Hadi (for M/s. J S Wad And Co.).
Adv. for the Respondents:
Dharav Shah, Dhawal Desai, Pranaya Goyal.
Respondent-in-person.
Judgment / Order of the Supreme Court Judgment Sudhanshu Dhulia, J.
1. The question which arises in these two appeals for our determination is that whether the borrower of a project loan, falls within the definition of ‘Consumer’ under the provisions of the Consumer Protection Act, 1986 (hereinafter, ‘the Act’).
2. These statutory appeals arise from the order dated 30.08.2023 passed by the National Consumer Disputes Redressal Commission, New Delhi (hereinafter, ‘NCDRC’) in Consumer Complaint No. 23/2021. The appellant before us in Civil Appeal No. 7483 of 2023 is the Chief Manager, Central Bank of India and has filed the appeal under Section 23 of the Act, assailing the finding arrived at by the NCDRC holding that there was a deficiency in service on part of the appellant and thus, it is liable to pay compensation to the respondent No. 1, which is M/s Ad Bureau Pvt. Ltd., (a company engaged in the business of branding, consulting & advertising).
3. On the other hand, Civil Appeal (Diary) No. 20192 of 2024 has been filed by M/s Ad Bureau Pvt. Ltd., challenging the quantum of compensation awarded by the NCDRC, on the ground that the same has been awarded inadequately. For the sake of convenience, we shall refer to the parties as per their respective status in Civil Appeal No. 7483 of 2023.
4. The NCDRC vide its order dated 30.08.2023 has allowed the Consumer Complaint filed by respondent No.1 herein and has 1448 [2025] 2 S.C.R.Supreme Court Reports directed the appellants 1 to pay a compensation of Rs. 75,00,000/- to respondent No.1 and to issue a certificate stating that the loan account of respondent No.1 with the Central Bank of India was settled and no outstanding dues remained in the said account and also holding that the Bank had wrongly reported the status of respondent No.1 as a defaulter to CIBIL, 2 which caused loss to the respondent No.1 in the market. Additionally, the appellants were also directed to pay to respondent No.1, litigation costs of Rs. 20,000/-.
5. At the outset, it would be necessary to state the relevant facts. On 28.04.2014, a Project Loan of Rs. 10 crores was sanctioned by the Central Bank of India in favour of respondent No.1, which is a private limited company carrying on advertising business. The purpose behind availing this loan was that respondent No. 1 was to engage in the post-production of a movie. A property located at old D.No. 61, new D. No. 194, St. Mary’s Road, Abhiramapuram, Chennai, which stood in the name of the Chairman and Managing Director of respondent No.1 was pledged as collateral for the loan. After availing the said loan, respondent No. 1 defaulted in repayment and its loan account and was classified as NPA3 on 04.02.2015. When respondent No.1 failed to repay the amount even after issuance of Demand Notice by the appellant-bank, a Possession Notice was issued on 21.05.2015 and pursuant to the same, symbolic possession of the property pledged as collateral for the loan was taken in terms of the provisions of the Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002 (hereinafter referred to as ‘SARFAESI Act’).
6. Thereafter, on 09.10.2015 the Bank filed an application under Section 19 (1) of Recovery of Debts Due to Banks and Financial Institutions Act, 1993 (hereinafter referred to as ‘RDDBFI Act’) before the Debts Recovery Tribunal, Chennai for recovery of an amount of Rs 4,65,39,715/-. This application came to be allowed by the Debts Recovery Tribunal, Chennai vide order dated 05.12.2016 and the Bank was held to be entitled to recover an amount of Rs.4,65,39,715/with interest @ 12% p.a. till the date of realisation along with costs. Pursuant thereto, a communication was addressed to the 1 Appellant Nos. 1, 2 & 3 are the Chief Manager, Mount Road Branch, Chennai; Field General Manager, Chennai; and the Managing Director & Chief Executive Officer of the Central Bank of India respectively. 2 Credit Information Bureau of India Limited.
3 Non-Performing Asset.
[2025] 2 S.C.R. 1449The Chief Manager, Central Bank of India & Ors. v. M/s Ad Bureau Advertising Pvt. Ltd & Anr.
appellant-bank by respondent No.1 offering a One-Time Settlement of Rs. 3.56 Crores and the offer was duly accepted by the appellant-bank.
7. Thereafter, the appellant-bank called upon respondent No.1 to pay the ‘delayed period interest’ which was computed as Rs. 14.43 lacs. Admittedly, this amount was also paid by respondent No.1 to the appellant-bank, pursuant to which ‘No-Dues Certificate’ was issued on 13.01.2017 and 20.03.2017 by the appellant-bank towards respondent No.1. Further, a ‘full-satisfaction memo’ was also filed before the DRT by the appellant-bank, wherein the factum of payment of the one-time settlement amount and delayed interest by respondent No. 1 was accepted by the appellant-bank.
8. The precise case of the respondent No. 1 before the NCDRC, as well as before this Court, has been that the appellant-bank was grossly negligent and deficient in providing banking services to respondent No. 1 and has consequently caused monetary damages and a loss of reputation to it. As per the ‘Master Circular on Wilful Defaulters’ 4 by the Reserve Bank of India (hereinafter, ‘RBI’), all nationalised banks and financial institutions have to report information regarding borrower accounts which are classified as doubtful and loss accounts with outstanding amount aggregating Rs. 1 Crore and above. These borrowers are classified and reported as ‘wilful defaulters’ by the respective banks and financial institutions to the RBI, which in turn, consolidates the entire information reported in the form of a list on a yearly basis. The grievance of respondent No. 1 towards the appellant-bank has been that the appellant-bank, despite issuing a No-Dues Certificate and despite filing a Full-Satisfaction Memo before the DRT, incorrectly reported the name of respondent No. 1 to RBI as a defaulter with a total outstanding amount of Rs. 4.17 Crores.
9. This incorrect reporting by the appellant-bank not only led to a significant loss of goodwill and reputation, but it also resulted in the respondent No. 1 losing an exclusive advertising tender/license by the Airports Authority of India, which although, was initially awarded to respondent No. 1 but was subsequently cancelled for the reason that a Bank Guarantee was required to be submitted, but the same could not be done, as when the respondent No.1 approached HDFC Bank for issuance of the same, the bank refused to do so upon finding the name of respondent No.1 in the list of wilful defaulters. 4 Circular No. DBOD No. BC/CIS/47/20.16.002/94 dated 23.04.1994. 1450 [2025] 2 S.C.R.Supreme Court Reports
10. Aggrieved by the wrongful reporting and the losses which it faced on account of the same, respondent No. 1 filed Consumer Complaint No. 23 of 2021 before the NCDRC. Vide Impugned Order dt. 30.08.2023, NCDRC partly allowed the complaint, holding that the appellant-bank was deficient in service and also engaged in an unfair trade practice. It was observed by the NCDRC that since the wrongful reporting by the appellant-bank constitutes a serious breach of duty, it is liable to compensate respondent No. 1 for the losses it has incurred and accordingly, the NCDRC awarded a compensation of Rs. 75,00,000/to respondent No. 1 which was to be paid jointly and severally by the appellants herein and also directed them to pay litigation costs of Rs. 20,000/-. Further, the appellants were directed to issue a certificate in favour of respondent No. 1, wherein it was to be stated by the appellant-bank that loan account of respondent No. 1 stood settled and no outstanding dues remained. The appellant-bank had to further state that it had been wrongly reporting the status respondent No. 1 as a ‘defaulter’ from 31.03.2017 till 30.06.2020.