M/S Godwin Construction Pvt. Ltd. v. Commissioner, Meerut Division & Anr.
- Citation
- 2025 INSC 1207; [2025] 10 S.C.R. 368
- Court
- Supreme Court of India
- Bench
- 2 Judges: Justice Ahsanuddin Amanullah, Justice Prashant Kumar Mishra
- Decided
- 8 Oct 2025
- Case number
- CIVIL APPEAL No. 7661/2014
- Sections
- 126, 33(4), 56(1), 2(17)
Not a certified copy. Text extracted from the judgment PDF published by the Supreme Court of India. Verify against the certified copy before relying on it. Source: Supreme Court of India, via the Indian Supreme Court Judgments dataset by Dattam Labs (CC-BY-4.0). Retrieved 17 Nov 2026, 12:21 am. Original source ↗
Preview: first 50% of the document.
[2025] 10 S.C.R. 368 : 2025 INSC 1207 M/s Godwin Construction Pvt. Ltd.
v.
Commissioner, Meerut Division & Anr.
(Civil Appeal No. 7661 of 2014)
08 October 2025 [Ahsanuddin Amanullah and Prashant Kumar Mishra,* JJ.] Issue for Consideration Whether the stamp duty on the instrument “Security Bond cum Mortgage Deed”, is chargeable under Article 40 or Article 57 of Schedule 1-B of the Indian Stamp Act 1899.
Headnotes† Indian Stamp Act 1899 – Article 40 or Article 57 of Schedule 1-B – Stamp duty on the instrument “Security Bond cum Mortgage Deed”, if chargeable u/Article 40 or Article 57 of Schedule 1-B:
Held: In matters of stamp duty, the decisive factor is not the nomenclature assigned to the instrument, but the substance of rights and obligations it embodies – Court is duty-bound to ascertain the true legal character of the instrument – In the instant case, the appellant executed a “Security Bond cum Mortgage Deed” in favour of the Meerut Development Authority – The instrument executed by the appellant fulfils the essential characteristics of a mortgage deed – In substance and effect, the deed confers a right over specified properties in favour of the Meerut Development Authority to secure performance of an obligation, while preserving the appellant’s interest until full discharge of obligation – The nomenclature “Security Bond cum Mortgage Deed” is, therefore, inconsequential, as it is the substance and operative provisions of the instrument which govern its character for the purposes of stamp duty – Further, it is apparent from the recitals of the instrument titled “Security Bond cum Mortgage Deed” executed by the appellant that only two parties are involved viz. the Meerut Development Authority and the appellant – The deed was not executed by a * Author [2025] 10 S.C.R. 369M/s Godwin Construction Pvt. Ltd. v. Commissioner, Meerut Division & Anr.
surety but by the principal debtor/appellant, the company, through its director – The company itself mortgaged the properties and not the director in his individual capacity – A company, though a juristic person, is not a sentient being, consequently, it must act through its directors – Thus, the properties were not mortgaged by a third party, but by the principal debtor itself, which does not attract Article 57 – In the absence of any surety, to attract Article 57 of the Indian Stamp Act, the deed executed by the appellant cannot be termed as a security bond – It, however, fulfils all the requirements of a mortgage deed, falling under the ambit of Article 40 of Schedule 1-B of the Indian Stamp Act – Impugned judgments not interfered with. [Paras 14, 17, 24-26] Indian Stamp Act 1899 – Article 57 of Schedule 1-B – Operation of, explained – Contract Act, 1872 – s.126 – “Contract of guarantee”, “surety”, “principal debtor” and “creditor”. [Paras 20-23] List of Acts Indian Stamp Act, 1899; Indian Contract Act, 1872.
List of Keywords Article 40 or Article 57 of Schedule 1-B of the Indian Stamp Act 1899; “Security Bond cum Mortgage Deed”; Security Bond or Mortgage Deed; Nature and substance of the deed; Chargeability of the instrument under the Indian Stamp Act, 1899; Stamp duty; Nomenclature; Not nomenclature assigned to the instrument; Substance of rights and obligations; Mortgage deed; Deed not executed by a surety but by the principal debtor; Section 126, Contract Act, 1872; “Contract of guarantee”; “Surety”; “Principal debtor”; “Creditor”.
Case Arising From CIVIL APPELLATE JURISDICTION: Civil Appeal No. 7661 of 2014 From the Judgment and Order dated 22.01.2013 of the High Court of Judicature at Allahabad in WP No. 31966 of 2012 With Civil Appeal No. 12552 of 2025 370 [2025] 10 S.C.R.Supreme Court Reports Appearances for Parties Advs. for the Appellant:
Jitendra Mohan Sharma, Ms. Kavita Jha, Sr. Advs., Akshat Sharma, Amrit Pradhan, Sandeep Singh, Pahlad Singh Sharma, Vaibhav Kulkarni, Aniket Deepak Agrawal, Aditeya Bali.
Advs. for the Respondents:
Shaurya Sahay, Aditya Kumar, Ruchil Raj, Bhakti Vardhan Singh. Judgment / Order of the Supreme Court Judgment Prashant Kumar Mishra, J.
1. Leave granted in SLP (Civil) No.36434 of 2014.
FACTUAL MATRIX IN CIVIL APPEAL NO. 7661 OF 2014
2. Civil Appeal No.7661 of 2014 calls in question the impugned order dated 22.01.2013 passed by the High Court of Judicature at Allahabad in Writ Petition No. 31966/2012, whereby the High Court dismissed the writ petition filed by the appellant, affirming the order dated 11.06.2012 passed by respondent No.1, which in turn affirmed the order dated 15.09.2010 passed by respondent No.2, directing the appellant to pay Rs.4,61,760/- (Rupees Four Lakh Sixty-one Thousand Seven Hundred and Sixty) as deficient stamp duty under Article 40(b) of Schedule 1-B of the Stamp Act, together with penalty of Rs.100/- along with interest at the rate of 1.5% per month from the date of execution of the instrument till recovery.
3. On 18.12.2006, the Meerut Development Authority allowed the appellant to develop a colony known as “Global City, Abdullahpur, Meerut”. On 19.12.2006, the appellant executed a “Security Bond cum Mortgage Deed” in favour of the Meerut Development Authority under Article 57 of Schedule 1-B of the Indian Stamp Act, 1899 to secure performance of all obligations relating to the development of the colony, including payment of external development charges and provision of requisite amenities. The appellant mortgaged specified plots of land under the deed, totalling 2,934.45 square meters. [2025] 10 S.C.R. 371M/s Godwin Construction Pvt. Ltd. v. Commissioner, Meerut Division & Anr.
4. The appellant transferred all their interest in the properties specified in the deed to the Meerut Development Authority, intending that they shall remain mortgaged. In case of default of liability, the Meerut Development Authority shall be entitled to sell the mortgaged properties to realize an amount of ₹1,00,44,000/- (Rupees One Crore and Forty-four Thousand). The appellant had also deposited an advance deposit of ₹15,00,000/- (Rupees Fifteen Lakh) and upon the full discharge of all obligations, the surety under the bond and obligation will be void. A stamp duty of ₹100/- was paid, in accordance with Article 57 of Schedule 1-B of the Indian Stamp Act.
5. On 16.02.2008, the Deputy Commissioner (Stamps), Meerut Circle, Meerut, issued a notice to the appellant stating that the stamp duty was payable under Article 40 of Schedule 1-B of the Indian Stamp Act, and initiated recovery proceedings under Section 33(4) for remaining deficit stamp duty of ₹4,61,660/- (Rupees Four Lakh Sixty-one Thousand Six Hundred and Sixty).
6. On 07.07.2010, the appellant filed objections to the notice dated 01.05.2008 before respondent No.2. By order dated 15.09.2010, respondent No.2 held that the instrument described as “Security Bond cum Mortgage Deed” was chargeable under Article 40 of Schedule 1-B of the Indian Stamp Act and not under Article 57 as claimed by the appellant. Accordingly, he confirmed the demand for deficit stamp duty of ₹4,61,660/- together with a penalty of ₹100/- totalling ₹4,61,760/- and interest at the rate of 1.5% per month with effect from the date of execution of the said instrument till the date of recovery.
7. Aggrieved by the order dated 15.09.2010 passed by respondent No.2, the appellant filed Stamp Appeal No.8/2010 under Section 56(1)(b) of the Indian Stamp Act before the respondent No.1. However, the said appeal was dismissed by respondent No.1 vide order dated 11.06.2012.
8. Aggrieved, the appellant preferred Writ Petition No.31966/2012 before the Hon’ble High Court. Vide judgment dated 22.01.2013, the High Court dismissed the writ petition, holding that the Security Bond cum Mortgage Deed dated 19.12.2006 was executed solely between the appellant and the Meerut Development Authority as a mortgage deed. In the absence of any surety or third party, it was chargeable under Article 40 of Schedule 1-B of the Indian Stamp Act, 1899. Pursuant to the above dismissal, the present Civil Appeal has been filed. 372 [2025] 10 S.C.R.Supreme Court Reports
FACTUAL MATRIX IN CIVIL APPEAL ARISING OUT OF SLP (C)
NO.36434/2014
9. The appellant applied for a business loan of Rs.1,66,00,000/- (Rupees One Crore and Sixty-six Lakh) from the Allahabad Bank. To ensure re-payment of loan, he executed a “Security Bond or Mortgage Deed” placing immoveable property being plot No.122-M measuring 0.202 hectares, situated in Village Jugauli Tappa Sirsia, Pargana Vinayakpur, Tehsil Nautanwa, District Maharajganj as security with the bank. The deed was executed on a stamp paper of ₹.100/- in compliance with Article 57 of Schedule 1-B of the Indian Stamp Act, 1899.
10. The deed was presented before Sub-Registrar for registration on 04.12.1995 which was forwarded to the Deputy Collector (Stamp), with his report dated 06.01.1996, observing that the document was a mortgage deed, and chargeable under Article 40, Schedule 1-B of the Indian Stamp Act, thus, indicated a stamp deficit of Rs.1,37,500/- (Rupees One Lakh Thirty-seven Thousand and Five Hundred). The Deputy Collector (Stamp) vide order dated 10.04.1997, concurred with the Sub-Registrar’s report and held that the deed in question was a simple mortgage deed chargeable with stamp duty at the rate of Rs.62.50 per thousand. Aggrieved thereto, appellant preferred Stamp Revision No.59/1997-98 but the same was dismissed. Assailing the orders dated 10.04.1997 and 10.08.2001; the appellant filed Writ Petition No.33415/2001 before the High Court. The High Court after dealing with the issue on merits, dismissed the writ petition, finding no perversity in the impugned orders.
SUBMISSIONS
11. Learned counsel for the appellants in both the Appeals submit that the instrument executed by the appellants should be charged for stamp duty as per Article 57 of Schedule 1-B of the Indian Stamp Act. Learned counsel further asserted that the subject deeds are not simplicitor mortgage deeds as defined under Section 2(17) of the Indian Stamp Act, 1899. Hence, the stamp duty cannot be levied under Article 40 of the Indian Stamp Act, 1899.
12. Per contra, the learned counsel for the respondents contended that the impugned orders have rightly held that the deeds executed by the appellants in favour of the Meerut Development Authority and the Allahabad Bank respectively are chargeable under Article 40 of [2025] 10 S.C.R. 373M/s Godwin Construction Pvt. Ltd. v. Commissioner, Meerut Division & Anr.
Schedule 1-B of the Indian Stamp Act, 1899. Learned counsel assert that the orders of the High Court do not require any interference.
13. The question which falls for our consideration in both the Appeals is whether the stamp duty on the instrument “Security Bond cum Mortgage Deed”, is chargeable under Article 40 or Article 57 of Schedule 1-B of the Indian Stamp Act 1899.
ANALYSIS
CIVIL APPEAL NO.7661 OF 2014
14. It is trite that, in matters of stamp duty, the decisive factor is not the nomenclature assigned to the instrument, but the substance of rights and obligations it embodies. The Court is duty-bound to ascertain the true legal character of the instrument. In the instant case, the appellant has executed a “Security Bond cum Mortgage Deed” in favour of the Meerut Development Authority. Unless the nature and effect of such an instrument are conclusively identified, the application of any provision for the determination of stamp duty on instruments under the Indian Stamp Act, 1899, cannot be undertaken. It is necessary to have regard to the operative recitals and clauses of the deed executed by the appellant. For this purpose, the relevant portions of the “Security Bond cum Mortgage Deed dated 19.12.2006 are extracted below: “STAMP DUTY RS 100/- IMPROVEMENT TRUST DUTY NILL TOTAL RS 100/- THIS SECURITY Bond CUM MORTGAGE DEED is being executed by surety to secure due performance of contract and for due discharge of liability. The stamp duty is being paid under Article 57 of the schedule I-B of the Indian Stamp Act, 1989, as amended in its application of Uttar Pradesh.
THIS INDENTURE IS MADE at Meerut on the 19 th day December 2006.
BETWEEN
Godwin Construction Pvt. Ltd. through Director Shri Jitender Bajwa R/o A-151, Defence Colony, Meerut hereinafter called SURETIES of the one part which expression shall, unless repugnant to the context or in consistent with the subject, include their heirs, executors and administrators etc.
374 [2025] 10 S.C.R.Supreme Court Reports