Satish Chander Sharma & Ors. v. State of Himachal Pradesh & Ors.
- Citation
- 2025 INSC 491; [2025] 5 S.C.R. 217
- Court
- Supreme Court of India
- Bench
- 3 Judges: Justice Surya Kant, Justice Dipankar Datta, Justice Ujjal Bhuyan
- Decided
- 15 Apr 2025
- Case number
- WRIT PETITION (CIVIL) No. 179/2018
Not a certified copy. Text extracted from the judgment PDF published by the Supreme Court of India. Verify against the certified copy before relying on it. Source: Supreme Court of India, via the Indian Supreme Court Judgments dataset by Dattam Labs (CC-BY-4.0). Retrieved 17 Nov 2026, 12:19 am. Original source ↗
Preview: first 50% of the document.
[2025] 5 S.C.R. 217 : 2025 INSC 491 Satish Chander Sharma & Ors.
v.
State of Himachal Pradesh & Ors.
(Writ Petition (Civil) No. 179 of 2018)
16 April 2025 [Surya Kant, Dipankar Datta and Ujjal Bhuyan,* JJ.] Issue for Consideration Issue arose as to whether the decision in State of H.P. v. Rajesh Chander Sood, upholding the cut-off date of 02.12.2004, is per incuriam; whether the aforesaid decision is binding on the petitioners; whether a writ petition under Article 32 of the Constitution is maintainable to directly or collaterally challenge a judgment of the Supreme Court.
Headnotes† Constitution of India – Article 32 – Judgment/Order of Supreme Court passed u/Article 136, not amenable to judicial review u/Article 32 – In a matter, High Court allowed the writ petitions filed by another group of petitioners directing the State to provide pension to the retired employees of the Himachal Pradesh State Forest Development Corporation Limited (Corporation) in terms of the Himachal Pradesh Corporate Sector Employees (Pension, Family Pension, Commutation of Pension and Gratuity) Scheme, 1999 – Said decision was reversed by a two-Judge Bench of this Court in State of H.P. v. Rajesh Chander Sood – Present petition u/Article 32 filed by the petitioners, retired officers of the Corporation challenging the decision in Rajesh Chander Sood as per incuriam, aggrieved by denial of pensionary benefits to them in terms of the 1999 Scheme discontinued vide the notification dated 02.12.2004, which carved out an exception for those who had opted for the scheme and had superannuated prior to 02.12.2004:
Held: In Rajesh Chander Sood, this Court held that the State Government was justified in postulating a cut-off date by which some of the employees governed by the 1999 Scheme (those who had retired prior to 02.12.2004 were entitled to draw pension under the 1999 Scheme whereas those who had not retired by the time * Author 218 [2025] 5 S.C.R.Supreme Court Reports the repeal notification was issued on 02.12.2004 were denied such benefit) – It was held that the State Government had the competence to repeal the 1999 Scheme and by doing so, it did not curtail the right of the employees to receive pension rather they would continue to receive pension under the erstwhile pension scheme however, would not get the additional benefits under the 1999 Scheme – This Court had given elaborate reasons while allowing the civil appeal and upholding the cut-off date of 02.12.2004 – Rajesh Chander Sood did not ignore any binding precedent and is not per incuriam – When this Court had set aside the judgment of the High Court, the claim of not only those petitioners but similarly situated employees (like the present petitioners) were also negatived – Rajesh Chander Sood is thus, binding on the petitioners – Furthermore, Judgment and order of this Court passed u/Article 136 of the Constitution of India is not amenable to judicial review u/Article 32 of the Constitution – Thus, there cannot be any challenge either directly or collaterally to the decision of this Court in Rajesh Chander Sood in a proceeding u/ Article 32 – Present writ petition is misconceived. [Paras 21.5, 22, 23, 28, 32] Administration of justice – Adjudication process – Principle of finality – Finality of lis, core facet of judicial system – Emphasized:
Held: Litigation which had concluded or had reached finality cannot be reopened – A litigant who is aggrieved by a decision rendered by Supreme Court in a special leave petition or in a civil appeal arising therefrom can seek its review by invoking the review jurisdiction and thereafter through a curative petition – But such a decision cannot be assailed in a writ proceeding u/Article 32 of the Constitution of India – If this is permitted, then there will be no finality and no end to litigation creating chaos in the administration of justice – Constitution of India – Article 32. [Para 30] Case Law Cited State of H.P. v. Rajesh Chander Sood [2016] 6 SCR 851 : (2016) 10 SCC 77 – held not per incuriam.
Naresh Shridhar Mirajkar v. State of Maharashtra [1966] 3 SCR 744 : AIR 1967 SC 1 – followed.
Sub-Inspector Sadhan Kumar Goswami v. Union of India [1996] Supp. 7 SCR 814 : (1997) 2 SCC 225; Indian Council for [2025] 5 S.C.R. 219Satish Chander Sharma & Ors. v. State of Himachal Pradesh & Ors. Enviro-Legal Action v. Union of India [2011] 9 SCR 146 : (2011) 8 SCC 161; Khoday Distilleries Ltd. v. Registrar General, Supreme Court of India [1995] Supp. 6 SCR 190 : (1996) 3 SCC 114 – relied on.
R.R. Verma v. Union of India [1980] 3 SCR 478 : (1980) 3 SCC 402; BALCO Employees’ Union v. Union of India [2001] Supp. 5 SCR 511 : (2002) 2 SCC 333; D.S. Nakara v. Union of India [1983] 2 SCR 165 : (1983) 1 SCC 305; Rupa Ashok Hurra v. Ashok Hurra [2002] 2 SCR 1006 : (2002) 4 SCC 388; A.R. Antulay v. R.S. Nayak [1988] Supp. 1 SCR 1 : (1988) 2 SCC 602; Omprakash Verma v. State of Andhra Pradesh [2010] 15 SCR 302 : (2010) 13 SCC 158; Green View Tea & Industries v. Collector (2002) 1 SCC 109; Indian Council for Enviro-Legal Action v. Union of India (2011) 8 SCC 161 – referred to. P.D. Nanda v. State of H.P., 2013 SCC Online HP 5151 – referred to.
List of Acts Constitution of India; Himachal Pradesh Corporate Sector Employees (Pension, Family Pension, Commutation of Pension and Gratuity) Scheme, 1999; Central Civil Services (Pension) Rules, 1972; Central Civil Services (Commutation of Pension) Rules, 1981. List of Keywords Writ Petition; Article 32 of the Constitution of India; Judgment of Supreme Court not amenable to judicial review under Article 32; Direct or collateral challenge to the judgment of the Supreme Court; Rajesh Chander Sood case; Not per incuriam; Binding precedents; Finality of lis; Principle of finality of an adjudication process; Review Petition; Curative Petition; Himachal Pradesh State Forest Development Corporation Limited; Himachal Pradesh Corporate Sector Employees (Pension, Family Pension, Commutation of Pension and Gratuity) Scheme, 1999; Denial of Pensionary Benefits; Administration of justice; Finality of an order of the Supreme Court.
Case Arising From CIVIL ORIGINAL JURISDICTION: Writ Petition (Civil) No. 179 of 2018 (Under Article 32 of The Constitution of India)
220 [2025] 5 S.C.R.Supreme Court Reports Appearances for Parties Advs. for the Petitioners:
Gopal Sankarnarayan, Sr. Adv., Anand Varma, Ms. Adyasha Nanda, Ms. Aditi Gupta.
Advs. for the Respondents:
Devadatt Kamat, Sr. Adv., Anubhav Sharma, Gaurav Prakash Pathak, Nishant Kumar, Rajesh Inamdar, Ajay Desai, Revanta Solanki, Abhyudaya Bajpai, Gopal Prasad, Ms. Shalya Agarwal. Judgment / Order of the Supreme Court Judgment Ujjal Bhuyan, J.
Heard learned counsel for the parties.
2. This is a petition filed by three petitioners under Article 32 of the Constitution of India. Petitioners are retired officers of Himachal Pradesh State Forest Development Corporation Limited (briefly ‘the Corporation’ hereinafter). They are aggrieved by denial of pensionary benefits to them in terms of the Himachal Pradesh Corporate Sector Employees (Pension, Family Pension, Commutation of Pension and Gratuity) Scheme, 1999 discontinued vide the notification dated 02.12.2004, which though carved out an exception for those who had opted for the scheme and had superannuated prior to 02.12.2004. Hence, they seek a direction to the respondents for payment of pension to them upon their superannuation in terms of the said scheme at par with similarly situated employees who had retired prior to 02.12.2004, by counting their pensionable service from the date of joining till the date of their superannuation.
3. This issue was earlier raised by a group of petitioners before the Himachal Pradesh High Court (‘High Court’ hereinafter) by filing writ petitions under Article 226 of the Constitution of India, the lead case being P.D. Nanda Vs. State of H.P.,1 CWP No. 4425 of 2009. The High Court had allowed the writ petitions vide the judgment and order dated 19.12.2013 by directing the State to provide pension to 1 2013 SCC Online HP 5151 [2025] 5 S.C.R. 221Satish Chander Sharma & Ors. v. State of Himachal Pradesh & Ors. the retired employees of the Corporation in terms of the aforesaid scheme. This decision was reversed by a two-Judge Bench of this Court in State of H.P. Vs. Rajesh Chander Sood. 2
4. Thereafter, the present writ petition came to be filed before this Court seeking the same relief. Various contentions have been raised including the one that the decision in Rajesh Chander Sood (supra) has ignored several binding precedents of this Court and is, therefore, a decision rendered per incuriam.
5. This Court issued notice vide the order dated 20.03.2018. In the said order, a two-Judge Bench of this Court, after observing that since correctness of this Court’s judgment in Rajesh Chander Sood (supra) has been questioned, requested the learned Chief Justice to place the matter before a three-Judge Bench. This is how the matter has been placed before the present Bench and heard accordingly.
6. Though learned senior counsel for the respondent-State has raised a preliminary objection as to maintainability of the present writ petition, we are of the view that such an objection may be considered while considering the stand of the respondents.
7. At the outset, it would be apposite to advert to the relevant facts.
8. The Corporation was incorporated under the Companies Act, 1956 pursuant to a notification dated 26.03.1974 issued by the Government of Himachal Pradesh. It is completely owned and controlled by the State Government inasmuch as 100% of the share capital of the Corporation is owned by the State of Himachal Pradesh.
9. Petitioner No. 1 was appointed as a Clerk in the Corporation on 29.10.1975. On 27.03.1981, he was promoted to the post of Junior Assistant. He was further promoted to the post of Senior Assistant(Senior Accountant) on 07.11.1984. He was promoted to the post of Office Manager(Junior) on 03.04.1989 and, thereafter, to the post of Office Manager (Senior) on 17.11.2011. Petitioner No. 1 superannuated from service on 31.01.2013.
9.1. Petitioner No. 2 was appointed as a Clerk in the Corporation on 15.02.1988. He was promoted to the post of Senior Clerk on 15.02.1993 and, thereafter, to the post of Junior Assistant
2 (2016) 10 SCC 77
222 [2025] 5 S.C.R.Supreme Court Reports on 01.01.1996. He was further promoted to the post of Senior Assistant on 07.09.2009 whereafter he was promoted to the post of Office Manager (Junior) from which post he superannuated on 30.09.2016.
9.2. Petitioner No. 3 was appointed to the post of Clerk in the Corporation on 05.12.1981. He was promoted to the post of Senior Clerk on 24.05.1985 and, thereafter, to the post of Junior Assistant on 25.04.1992. He was further promoted to the post of Senior Assistant on 24.12.1993. On 08.11.2013, petitioner No. 3 was promoted to the post of Office Manager (Junior) whereafter he superannuated on 30.11.2014.
10. It is stated that following the revision of pay scales of government employees by the State Government, the Corporation also allowed such revision of pay scales.
11. Since the employees of government corporations like the Corporation enjoyed parity with employees of the State Government qua all conditions of service, such as, pay scales, allowances etc., the State Government issued a notification dated 29.10.1999 whereby employees of government corporations i.e. state public sector undertakings like the Corporation were extended parity even as regards pensionary benefits. This scheme was called the Himachal Pradesh Corporate Sector Employees (Pension, Family Pension, Commutation of Pension and Gratuity) Scheme, 1999 (referred to hereinafter as ‘the 1999 Scheme’) and came into effect on and from 01.04.1999. It was mentioned that all pensionary benefits of the employees of the corporate sector were to be determined in accordance with the provisions laid down in the Central Civil Services (Pension) Rules, 1972 and the Central Civil Services (Commutation of Pension) Rules, 1981, as amended, and adopted by the Himachal Pradesh Government for the state government employees. The 1999 Scheme contemplated exercise of option by the employees of the corporate sector as to whether he or she would be governed under the existing statutory provisions or be governed under the 1999 Scheme which contemplated creation of a pension fund. The entire amount of contribution of the concerned public sector undertaking including interest thereon to the Contributory Provident Fund (CPF) upto 31.03.1999 were to be transferred to the corpus fund (pension fund) to be administered and maintained by the Government of [2025] 5 S.C.R. 223Satish Chander Sharma & Ors. v. State of Himachal Pradesh & Ors. Himachal Pradesh in the Finance Department. It was clarified that the existing employees who had opted for the 1999 Scheme would automatically forfeit their claim to the employers’ share of CPF including interest thereon to the State Government upto 31.03.1999. However, the amount of their subscriptions alongwith interest would be transferred to the General Provident Fund (GPF) account, to be allotted and maintained by the concerned public sector undertaking.
12. It is stated that the Corporation had amended its byelaws in order to implement the 1999 Scheme. The three petitioners had exercised their option in favour of the 1999 Scheme since this scheme provided for higher pensionary benefits.
13. It appears that reservations were expressed regarding the financial stability of the 1999 Scheme. In the above backdrop, the State Government constituted a High Level Committee (‘Committee’ hereinafter) in 2003 (21.01.2003) to review the financial viability of the 1999 Scheme. After a detailed analysis, the Committee submitted a report on 28.10.2003. The Committee was of the view that the 1999 Scheme was not viable on a self-sustaining basis for the following reasons:
i) uncertainty in the rate of interest regime;
ii) declining recruitment in the corporate sector would deplete the size of the corpus to be created and it would be difficult to honour liabilities accruing after 10-12 years;
iii) the pension plan envisages payment of pension to corporate sector employees as is being paid to the government employees. Government employees at present are entitled to pension @ 50% of the basic pay last drawn with linkage to their dearness allowance.
This return does not appear to be possible from the pension fund proposed to be created for corporate sector employees.
14. After considering the aforesaid report, Government of Himachal Pradesh in the Finance Department issued a notification dated 02.12.2004 whereby the 1999 Scheme was repealed with immediate effect. It was clarified that consequent upon the repeal, barring the employees who had retired from service w.e.f. 01.04.1999 till the date 224 [2025] 5 S.C.R.Supreme Court Reports of notification i.e. 02.12.2004, other employees would continue to be covered under those provisions which were applicable to them as on 31.03.1999. While clarifying that the public sector undertakings would be the pension sanctioning/ disbursing authority, the employers’ share of CPF including interest thereon was transferred to the respective public sector undertakings who were required to form a pension fund. In so far those employees of the public sector undertakings who had retired from service during the period w.e.f. 01.04.1999 till the date of publication of the notification i.e. 02.12.2004, the repeal notification stated as follows:
Notwithstanding such repeal, the employees of Himachal Pradesh corporate sector who retired from service w.e.f. 01.04.1999 till the date of publication of this notification shall continue to be governed under the provisions of the scheme so repealed; provided such retired employees had opted for such scheme and had otherwise become eligible for pension under the scheme.
15. A large number of writ petitions were filed before the High Court assailing the notification dated 02.12.2004 and seeking a direction that pension of the retired employees of the Corporation should be paid as per the 1999 Scheme. High Court vide the judgment and order dated 19.12.2013 allowed all the writ petitions. The cut-off date 02.12.2004 was declared ultra vires but instead of declaring the notification dated 02.12.2004 as unconstitutional, the same was read down by including the writ petitioners and similarly situated employees who had become members of the 1999 Scheme and had retired after 02.12.2004 as well as those employees who were already in service when the 1999 Scheme was notified and had become members of that scheme and would retire henceforth as eligible for pension under the 1999 Scheme.
16. The aforesaid decision of the High Court was assailed by the State before this Court in Rajesh Chander Sood (supra). A two-Judge Bench of this Court held that it was well within the authority of the State Government in exercise of its administrative powers which it had exercised by issuing the impugned repeal notification dated 02.12.2004 to fix a cut-off date for continuing the right to receive pension for some and denying the same to others. The Bench further held that the government was free to alter its earlier administrative decision and policy though it should be in consonance with all legal [2025] 5 S.C.R. 225Satish Chander Sharma & Ors. v. State of Himachal Pradesh & Ors. and statutory obligations. The Bench noted that it was not a case where the rights which had accrued to the employees under the Employees’ Provident Fund Scheme, 1995 under which the employees were covered prior to their opting for the 1999 Scheme, had in any manner been altered to their disadvantage. All that the repeal notification dated 02.12.2004 says is that the concerned employees would be entitled to all the rights which had accrued to them under the Employees’ Provident Fund Scheme, 1995 and not under the 1999 Scheme. In so far the bona fides of the State Government were concerned, the Bench observed that the State Government as a welfare measure had ventured to honestly extend some post-retiral benefits to the employees of independent legal entities like the Corporation on the mistaken belief, arising out of a miscalculation, that the same could be catered out of the available resources. This measure was adopted by the State Government not in its capacity as the employer of the respondent-employees but as a welfare measure. When it became apparent that the welfare measure extended by the State Government could not be sustained as originally understood, the same was withdrawn. Thus, the action of the State Government was bona fide. State Government had taken a conscious decision and the classification made by the State Government by fixing 02.12.2004 as the cut-off date was reasonable and justifiable in law; it also had a nexus to the object sought to be achieved. In the circumstances, the decision of the High Court was interfered with.
17. Mr. Gopal Sankaranarayan, learned senior counsel for the petitioners submits that the present proceeding is concerned with the pensionary rights and entitlement of the petitioners. This is also concerned with the correctness of the judgment rendered in Rajesh Chander Sood (supra). This Court while issuing notice vide the order dated 20.03.2018, prima facie, agreed with the contention of the petitioners that the judgment in Rajesh Chander Sood (supra) required reconsideration by a three-Judge Bench.
17.1. Learned senior counsel submits that the judgment in Rajesh Chander Sood (supra) is not good law and is per incuriam as it fails to consider binding precedents of coordinate and larger benches of this Court. Further, in the said judgment, the Bench contradicted itself by acknowledging the vested right of the employees under the 1999 Scheme but denying the benefits accruing therefrom to them.
226 [2025] 5 S.C.R.Supreme Court Reports
17.2. Learned senior counsel has referred to paragraphs 69, 70, 71 and 72 of the judgment in Rajesh Chander Sood (supra) and submits that the Bench had recorded a finding that having exercised their option for the 1999 Scheme and having forgone all their rights under the Employees Provident Fund Scheme, 1995, the employees concerned would be covered by the 1999 Scheme. As soon as they came to be covered by the 1999 Scheme, a contingent right came to be vested in them. As a matter of fact, the Bench had rejected the contention of the State that the rights of the employees under the 1999 Scheme would be vested only upon attaining the age of superannuation and accepted the contention advanced by the employees that any employee governed by a pension scheme, would be entitled to the benefits therefrom on attaining the qualifying service immediately on his enrolment in the said scheme, particularly, when they had expressly chosen to forgo their rights under the Employees’ Provident Fund Scheme, 1995.
17.3. Adverting to clause 1(2) of the 1999 Scheme, it is submitted by the learned senior counsel for the petitioners that the terms of clause 1(2) are clear and unambiguous. By way of incorporation, the Central Civil Services (Pension) Rules, 1972 and the Central Civil Services (Commutation of Pension) Rules, 1981, stood applicable to the employees upon their opting for the 1999 Scheme.
17.4. In Rajesh Chander Sood (supra), after acknowledging the vested right of the pensioners, this Court considered the issue of cut-off date. He submits that while this Court has upheld fixation of a cut-off date for extending better and higher pensionary benefits, there are no precedents whereby a cut-off date for discontinuing the right to receive pension, inter se, a homogeneous class has been sustained. He submits that reliance placed on the decisions of this Court in R.R. Verma Vs. Union of India 3 and BALCO Employees’ Union Vs. Union of India,4 was wholly misplaced as those two decisions were rendered in different contexts.
3 (1980) 3 SCC 402
4 (2002) 2 SCC 333
[2025] 5 S.C.R. 227Satish Chander Sharma & Ors. v. State of Himachal Pradesh & Ors.
17.5. He further submitted that the judgment in Rajesh Chander Sood (supra) sustaining the retrospective withdrawal of the 02.12.2004 notification whereby and whereunder pensionary rights of only those who had superannuated between 01.04.1999 and 02.12.2004 were saved as opposed to saving such rights of all those employees who were in service between 01.04.1999 and 02.12.2004 was explicitly contrary to the principles laid down by this Court in a large number of judgments. If the 1999 Scheme had to be repealed due to the purported object i.e. financial burden on the State, repealing of the same by not saving the rights of all those already covered under the 1999 Scheme would be violative of Article 14 of the Constitution of India.
17.6. Learned senior counsel submits that the cut-off date postulated by the notification dated 02.12.2004 providing that benefits under the 1999 Scheme would be available to those who had retired between 01.04.1999 and 02.12.2004 (date of the notification) thereby dividing a homogeneous class without having any reasonable nexus with the object sought to be achieved would be violative of Article 14 of the Constitution of India. In this connection, he has referred to and relied upon the Constitution Bench decision of this Court in D.S. Nakara Vs. Union of India. 5 He submits that prior judgments of this Court wherein similar cut-off dates based on the date of retirement were struck down by this Court were not considered in Rajesh Chander Sood (supra).
17.7. Mr. Gopal Sankaranarayan, learned senior counsel submits that the right to receive pension is a vested right and once the petitioners had opted for the 1999 Scheme, the same could not have been withdrawn, that too, unilaterally on the ground that the State did not have the financial means to support the scheme. Right to receive pension is not dependent upon the finances of the State. It was improper for the State Government to shrug away its responsibility post-introduction of the 1999 Scheme by labelling it as a self-financing pension fund created under the 1999 Scheme. This critical aspect was over-looked in Rajesh Chander Sood (supra).
5 (1983) 1 SCC 305
228 [2025] 5 S.C.R.Supreme Court Reports
17.8. He further submits that contention of the employees based on Article 300A of the Constitution of India was also summarily rejected by the Bench without any independent analysis. When this Court had recognized that the 1999 Scheme created a vested right on the employees, such a statutory right to receive pension would be in terms of the Central Civil Services (Pension) Rules, 1972. Such a statutory right therefore has to be construed as a property right under Article 300A of the Constitution of India.
17.9. He, therefore, submits that Rajesh Chander Sood (supra) is not a good law and is per incuriam. The present writ petition seeking pensionary rights of the petitioners as per the 1999 Scheme may, thus, kindly be allowed by this Court.
18. Per contra, Mr. Devadatt Kamat, learned senior counsel representing the State of Himachal Pradesh submits that the present writ petition filed under Article 32 of the Constitution of India is totally misconceived inasmuch as the issue raised in the writ petition i.e. entitlement of the petitioners to pension under the 1999 Scheme at par with similarly situated employees of the Corporation who had retired between 01.04.1999 and 02.12.2004 has already been decided by this Court in Rajesh Chander Sood (supra) . On this ground alone, the writ petition is liable to be dismissed.
18.1. Thereafter, learned senior counsel has adverted to the facts of the present case and submits that all the issues raised in the present proceeding were raised in Rajesh Chander Sood (supra) and adjudicated by this Court.
18.2. Learned senior counsel submits that the High Court had allowed the earlier batch of writ petitions vide the judgment and order dated 19.12.2013. This was challenged by the State before this Court in Rajesh Chander Sood (supra) which came to be decided on 28.09.2016. Though the present petitioners had superannuated before that, they did not join the aforesaid proceedings. As a matter of fact, they did not also participate in the proceedings before the High Court. Much after their superannuation, they filed the present writ petition. There is, thus, considerable delay and laches on the part of the petitioners in approaching this Court which would, therefore, disentitle them to any relief.
[2025] 5 S.C.R. 229Satish Chander Sharma & Ors. v. State of Himachal Pradesh & Ors.
18.3. Learned senior counsel vehemently argues that the present writ petition is nothing but a collateral challenge to a binding judgment of this Court in Rajesh Chander Sood (supra). It is not open to the petitioners to raise the same set of grounds urged in Rajesh Chander Sood (supra) which were rejected by this Court. A writ petition cannot be filed to doubt the correctness of a decision of this Court, he submits.
18.4. Learned senior counsel submits that the principle of per incuriam is not at all attracted to the facts of the present case. There is no glaring omission of law and precedent to constitute per incuriam.
18.5. On the merits of the case, learned senior counsel submits that financial viability or non-viability was a valid consideration taken into account by the State while issuing the repeal notification. The High Level Committee had examined the issue threadbare and, thereafter, submitted report. Based on the report of the High Level Committee, the repeal notification was issued.