Not a certified copy. Text extracted from the judgment PDF published by the Supreme Court of India. Verify against the certified copy before relying on it. Source: Supreme Court of India, via the Indian Supreme Court Judgments dataset by Dattam Labs (CC-BY-4.0). Retrieved 17 Nov 2026, 12:21 am. Original source ↗
Preview: first 50% of the document.
[2025] 2 S.C.R. 1295 : 2025 INSC 259 State of Odisha & Ors.
v.
Sudhansu Sekhar Jena (Civil Appeal No. 2803 of 2025)
21 February 2025 [Sudhanshu Dhulia* and Ahsanuddin Amanullah, JJ.] Issue for Consideration Issue arose as regards the computation of pensionary benefits of Job contract employees, only such period of their service as ‘Job Contractors’ to be counted for pensionary benefits as was sufficient to entitle them for pension or the entire period of Job Contract Employment; and the order of the Division Bench of the High Court dismissing the writ appeals filed by the State due to inordinate delay.
Headnotes† Service law – Odisha Civil Services (Pension) Rules, 1992 – r.18 (6) – Pensionary benefits – Computation, of employees employed as a ‘Job Contractor’ – Only such period of their service as ‘Job Contractors’ to be counted for pensionary benefits as was sufficient to entitle them for pension or the entire period of Job Contract Employment – Order passed by the Single Judge of the High Court that the entire service period be counted for calculation of pension of Job Contract employees – Writ appeals thereagainst by the State – Dismissed due to inordinate delay in filing the appeals – Challenge to: Held: Order of the Single Judge of the High Court not sustainable – Unable to grant relief to respondents-Job Contract employees that has been granted by the Court to work-charged employees – Under the 1992 Rules, clear distinction between the work-charged establishment and job contract establishment, however, the 1992 Rules and the distinction under the law not challenged before any Court – Thus, not in a position to give a finding as to whether the distinction between the two is artificial, being only a difference of nomenclature, and also whether effectively, they both are performing * Author 1296 [2025] 2 S.C.R.Supreme Court Reports regular work – Nevertheless, the State has been pursuing these cases in extreme careless and lethargic manner – Delay caused by them is inexcusable – Thus, the State to pay cost of Rupees One Lakh Fifty Thousand to the employees concerned in cases belatedly filed. [Paras 10, 14, 16, 18, 20] Odisha Civil Services (Pension) Rules, 1992 – r.18 sub rule 3 and 6 – Work charged employees and job contractors – Distinction between:
Held: Work-charged employees are those who have worked in the establishment for a period of five years or more without interruption and are subsequently appointed to the same or another post in temporary or substantive capacity in a pensionable establishment, the period of service rendered by him/her in a work-charged establishment to qualify for pension under the Rules – As regards the job contract employee, after he/she is brought in pensionable establishment, only that much period as job contract service to be added to regular service as would make him qualify or eligible for pensionary benefits. [Para 15] Deprecation – Inordinate delay – Procedural lapses by State authorities and Land Records office Surveys Office – Matters handled in a careless, casual and lethargic manner both in the High Court and before this Court, causing inordinate delay, which was never explained in any satisfactory manner – Thus, the State to pay Rupees One Lakh Fifty Thousand, to the employee concerned. [Paras 3, 20] Case Law Cited Settlement Class-IV Job Contract Employees Union, Balasore v. State of Orissa & Ors., O.J.C No. 2147/1991; Bhagaban Pattnaik v. State of Orissa, T.A No. 11/1993; Nityanand Biswal v. State of Orissa & Ors., O.A No. 3020(C)/2003; All Orissa Settlement and Land Consolidation Non-Gazetted Technical Officers Association v. State of Orissa & Ors., O.A No. 3665(C) of 2001; State of Orissa v. Nityanand Das & Ors., W.P(C) No. 11503/2008; Judhistir Padhy v. State of Odisha & Ors., WPC (OAC) No. 2276/2012; Chintamani Panda v. State of Odisha & Ors., W.P.C (OAC) No. 3741/2015; Pitambar Hota v. State of Odisha, W.P.C (OAC) No. 2622/2015; Prem Singh v. State of Uttar Pradesh and Others [2019] 11 SCR 1075 : (2019) 10 SCC 516; Uday Pratap Thakur and Another v. [2025] 2 S.C.R. 1297State of Odisha & Ors. v. Sudhansu Sekhar Jena The State of Bihar and Others [2023] 4 SCR 530 : (2023) SCC OnLine SC 527 – referred to.
List of Acts Constitution of India; Odisha Civil Services (Pension) Rules, 1992; Orissa Work Charged Employees (Appointment and Conditions of Service) Instructions, 1974; Orissa Consolidation of Holdings and Prevention of Fragmentation of Land Act, 1972.
List of Keywords Pension; Work charged employees; Work-charged establishment; Job contractors; Inordinate delay; Courts do not rescue those who sleep over their rights; Calculation of pension; Service to be counted for pension; Carelessness by State; Cost of Rupees One Lakh Fifty Thousand to the employees; Pensionary benefits. Case Arising From CIVIL APPELLATE JURISDICTION: Civil Appeal No. 2803 of 2025 From the Judgment and Order dated 20.11.2023 of the High Court of Orissa at Cuttack in WA No. 1134 of 2023 With Civil Appeal Nos. 2815, 2816, 2809, 2810, 2811, 2818, 2819, 2812, 2813, 2814, 2820, 2826, 2827, 2828, 2830, 2831, 2832, 2833, 2835, 2836, 2837, 2839, 2841, 2842, 2843, 2844, 2846, 2847, 2852, 2856, 2860, 2861, 2865, 2871, 2872, 2874, 2880, 2884, 2817, 2821, 2822, 2823, 2824, 2825, 2834, 2838, 2840, 2845, 2848, 2849, 2850, 2851, 2853, 2854, 2855, 2857, 2858, 2859, 2862, 2863, 2864, 2866, 2867, 2868, 2869, 2870, 2873, 2875, 2876, 2877, 2878, 2879, 2881, 2882, 2883, 2885, 2886, 2887, 2888, 2889, 2890, 2891, 2892, 2893, 2894, 2895, 2896, 2897, 2899, 2900, 2901, 2903, 2904, 2906, 2915, 2916, 2917, 2936, 2829, 2944, 2945, 2898, 2902, 2905, 2949, 2907, 2908, 2909, 2910, 2911, 2912, 2913, 2914, 2918, 2919, 2920, 2921, 2922, 2923, 2951, 2924, 2925, 2926, 2927, 2928, 2929, 2930 2931, 2956, 2932, 2959, 2960, 2961, 2933, 2965, 2934, 2935, 2974, 2982, 2987, 2992, 2938, 2939, 2940, 2942, 2943, 2946, 2948, 2950, 2953, 2955, 2962, 2963, 2964, 2966, 2967, 2968, 2975, 2976, 2978, 2979, 2980, 983, 2984, 2985, 2986 2989, 2990, 2991, 2993, 2994, 2995, 2996, 2997, 2998, 2999, 3000, 3001, 3002, 3004, 3005, 3006, 3007, 3008, 3009, 3010, 3011, 3012, 1298 [2025] 2 S.C.R.Supreme Court Reports 3013, 3015, 3017, 3019, 3020, 3021, 3022, 3023, 3025, 3026, 3029, 3030, 3031, 3033, 3034, 3035, 3042, 3046, 3052, 2957, 2977, 2981, 3014, 3041, 3045, 3051, 2970, 3040, 3048, 3049, 3050, 3060, 2969, 2972, 3027, 3039, 2937, 2952, 2988, 3003, 3016, 3018, 3024, 3028, 3032, 3036, 3037, 3038, 3047, 3053, 3054, 3055, 3056, 3057, 2954, 2973, 3067, 3063-3064, 2971, 3082, 3086, 3103, 3061, 3062, 3077, 3080, 3087, 3090, 3099, 3058, 3106, 3065, 3091, 3100, 3105, 3094, 3097, 3098, 3101, 3069, 3071, 3088, 3108, 3070, 3074, 3089, 3109, 3107, 3085, 3093, 3104, 3072, 3079, 3068, 3073, 3075, 3076, 3078, 3096, 3066, 2941, 2947, 2958, 3043, 3044, 3059, 3083, 3111, 3102, 3110, 3092, 3084, 3113, 3095, 3112, 3114, 3115, 3081, 3116 and 3117 of 2025.
Appearances for Parties Dr. Sandeep Singh, Amicus Curiae.
Advs. for the appearing parties:
Pitambar Acharya, Advocate General, Paramjit Singh Patwalia, Rakesh Kumar Khanna, Ashok Kumar Panigrahi, Sr.Advs., Ankit Agarwal, Ms. Viyushti Rawat, Shibashish Misra, Niranjan Sahu, Prasenjeet Mohapatra, Kiran Kumar Patra, Preetish Sahu, Dhananjaya Mishra, Nikhil Bhatia, Ayan Rai, Som Raj Choudhury, Ms. Shrutee Aradhana, Prashant Kumar, Prakash Ranjan Nayak, Debasis Jena, Animesh Dubey, Gaurav Khanna, Ms. Natasha Sahrawat, Ms. Deepali Bhanot, Gautam Barnwal, Rudraksh Pandey, Ms. Alisha Roy, Ms. Samapika Biswal, Aman Kumar Yadav, Rohit Amit Sthalekar, Shashank Singh, Purnendu Bajpai, Ms. Sharmila Upadhyay, Ramendra Mohan Patnaik, Subhasish Mohanty, Mata Prasad Singh, Vishvanath Agarwal, Pritam Singh, Amit Srivastava, Ms. Ranjita Sahu, Ms. Pritama, Manaj Sarkar, Srisatya Mohanty, Naveen Kumar, Ms. Aprajita Bhardwaj, Shourajeet Chakravarty, Nitesh Bhandari, Ms. Stuti Bisht, Prabhat Kumar Rai, Maitreya, Aditya Goyal, Aditya Kumar Singh, Bhaskar Bhushan, Ms. Esha Kumar, Utkarsh Chandra, Esha Kumar, Ujjawal Rai, Joby P. Varghese, Shubhranshu Padhi, Jay Nirupam, D. Girish Kumar, Pranav Giri, Ekansh Sisodia, Anjuman Tripathy, Chandra Vardhan Singh, Ardhendu Pratap Swain, Som Raj Choudhury, Ms. Shrutee Aradhana, Ms. Samapika Biswal, Ms. Soumya Sannidhanam, Aman Kumar Yadav, Niranjan Sahu, Pabitra Kumar Biswal, Mrs. Durga Devi Panda, Harisha S.R., Thomas Oommeen, Sanjeev Kumar, Gautam Kumar Laha, Subhransh Dash, Aldanish Rein, [2025] 2 S.C.R. 1299State of Odisha & Ors. v. Sudhansu Sekhar Jena Anshuman Siddharth Nayak, Devesh Pratap Singh, Rahul Kulhare, Gagan Singh Parmar, Pabitra Kumar Biswal, Thomas Oommen, Mrs. Durga Devi Panda, Sachin Kumar Verma, Ms. Bhanu Kapoor, Ms. Arushi Jindal, Krishna, Amit Kr.Singh, Ms. K.Enatoli Sema, Ms. Chubalemla Chang, Prang Newmai, A Deb Kumar, Binod Ch. Sabat, K C Kaushik, Tapas Das, Ms. Jay Jaimini Pandey, Satish Pandey, Merusagar Samantaray, Ruturaj Satapathy, Abinash Barik, Ms. Lhingneivah, Ms. Ayushi Upadhyay, Avneesh Arputham, Ankit Sharma, Kedar Nath Tripathy, Aditya Narayan Tripathy, Gyanadutta Chouhan, Raghunath Pathak, Sachin Yadav, Suresh Chandra Tripathy, Merusagar Samantaray, Ruturaj Satapathy, Abinash Barik, Ms. Lhingneivah, Ms. Ayushi Upadhyay.
Judgment / Order of the Supreme Court Judgment Sudhanshu Dhulia, J.
1. Delay condoned. Leave granted.
2. In all these appeals which are before this Court, the State of Odisha has challenged the order of the Division Bench of the Orissa High Court by which their Writ Appeals were dismissed due to inordinate delay in filing of Writ Appeals. Even this Court had earlier dismissed a few Special Leave Petitions on the same dispute, which were belatedly filed even before this Court. All the same, we are now examining the cases on its merits considering the importance of the matter(s). Nevertheless, the casual manner in which the State authorities, particularly the concerned department of the State and the Land Records office Surveys Office have handled the matters is a matter of concern.
3. It is not a case concerning a few employees, rather it affects a large number, and in turn, the State Exchequer. It is for this reason that we were persuaded to look into these matter(s), although initially, we were not inclined to interfere, considering the lethargic approach of the State in pursuing these matters, and the inordinate delay caused, which was never explained in any satisfactory manner. The State though kept filing one Special Leave Petition after another before this Court, not in one go but one after another, most of them belatedly, to complete a mere formality. For this reason, many of 1300 [2025] 2 S.C.R.Supreme Court Reports these petitions have been dismissed on the ground of delay itself as stated earlier, as Courts do not come to rescue those who sleep over their rights. Be it the State. The liability of the State on this issue will be addressed towards the end. Now, since we are taking up these matters, what will be the fate of the already dismissed petitions after our determination, we will address at the end.
4. In the State of Odisha, apart from regular employees who are working on sanctioned posts in various departments of the State, there are also a large number of employees, who were working as ‘Job Contractors’, who are mainly engaged for purposes of survey and preparation of maps and for the purposes of consolidation of land holdings etc. Their services were not pensionary services and thus even when they had put in long years of service as Job Contractors their services were not counted for pensionary benefits, and they were not given any pension post their retirement. The Rules which were applicable in the State of Odisha at the relevant point of time with which we are concerned are known as Odisha Civil Services (Pension) Rules, 1992 (hereinafter referred to as “Odisha Pension Rules, 1992”).
5. Then a case came up before the Division Bench of the Orissa High Court, i.e. Settlement Class-IV Job Contract Employees Union, Balasore v. State of Orissa & Ors. (O.J.C No.2147/1991) (hereinafter “Job Contract Employees Union”), which was decided on 24.03.1992. The High Court considered the non-payment of pension to Job Contractors as an unfair practice and even violative of Article 14 of the Constitution of India. Many of the Job Contractors were subsequently regularised in service but in most cases, this happened towards the end of their service where these employees had not completed the mandatory period of pensionable service which was 10 years. Hence, the Job Contractors though regularised in service before their retirement, were still not entitled for pension. The High Court in the said judgment said as under:
“13. … This apart, for the purpose of calculating the pensionary benefit, so much of their earlier service period shall be reckoned, even if there had been breaks in their employment, so as to make them eligible for pension. The necessity of giving this direction has been felt because, if service rendered after regularisation alone shall be counted [2025] 2 S.C.R. 1301State of Odisha & Ors. v. Sudhansu Sekhar Jena for pensionary benefit, most of the present incumbents would be denied the same, because to earn pension, ten years minimum service is necessary, which most of the incumbents at hand would not put in after regularisation as they would retire before completing this period having been appointed two decades back.”
The State of Odisha subsequently published an Office Memorandum dated 12 th December, 1997 where it repeated what has been said by the High Court in its Division Bench Judgment, while counting a part of the service of Job Contractors for grant of pension: “2. According to Finance Department Resolution No.
22764-F, dated the 15 th May 1997, the job contract employees appointed prior to the 12 th April 1993 (after which there is a ban for engagement of such employees) under the administrative control of different Departments can be brought over to the posts created under regular/ pension establishment after completion of 10 years, service as job-contract employees subject to fulfilment of certain conditions and stipulations outlined therein. According to the provisions contained in the said Office Memorandum, the date of regularisation shall be reckoned as the first appointment to the service for pension and other benefits. It has come to the notice of the Government that some of the job-contract employees are absorbed under the regular establishment almost towards the end of their service and become ineligible to get the pensionary benefits due to length of regular Government service in pensionable establishment. This has caused hardship to such type of employees.
3. The Hon’ble High Court of Orissa in their judgment dated the 24 th January, 1992 in O.J.C. No. 2147/91 directed that ‘for the purpose of calculating the pensionary benefit, so much of their service period shall be reckoned, even if there had been breaks in their employment, so as to make them eligible for pension’. The Hon’ble Orissa Administrative Tribunal have also in their judgment in O.A. No. 1545 (C)/96 have categorically directed to count that much period of job-contract service of the employees which will make them eligible for pensionary benefits.
1302 [2025] 2 S.C.R.Supreme Court Reports
4. After careful consideration of the matter, State Government have been pleased to decide that for the purpose of pensionary benefits only, so much of their job-contract service period shall be added to the period of qualifying service in regular establishment as would render them eligible for pension. Addition of that portion of job-contract service shall not be counted for calculation of gratuity.” Thereafter, in the year 2001, an amendment was finally brought in the Odisha Pension Rules, 1992 wherein sub-Rule 6 was added to Rule 18 of the said Rules, which reads as under: